48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR)UPRERADelayed 95 mo
Home › Projects › Moradabad › 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR)

48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR)

UPRERADelayed 95 moRegisteredupdated 4 Aug 2026

48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) is a RERA-registered real-estate project in Moradabad (RERA ID UPRERAPRJ13007). Its RERA-registered completion deadline (3 Sept 2018) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
95 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹5
Land area
not reported
Units (from plan)
48
Density (derived)
not reported
Towers
not reported
Config
OTHER
Carpet
45–45
Registered
28 Sept 2017

Basic details

RERA IDUPRERAPRJ13007
Applicant typeCompetent authority
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start4 Sept 2016
Original start4 Sept 2016
Project duration24
AddressMoradabad, Moradabad

Registration & timeline

RERA registered28 Sept 2017
Promised completion3 Sept 2018
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹11,500

Inventory

derived from unit plan
Total units · towers · floors48 · 1 · 1 (units from plan)
ConfigurationUnitsCarpet area
OTHER4845
Towers as filed3
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
022 Jan 201621 Jan 20213 Sept 2018

Land & documents

2 filings
KhasraAreaType
3878000—
3878000Khasra
Registry & lease deeds
Registry no.DateTypeArea
278620 Jun 1991——

Nearby projects

Moradabad

Other projects registered in Moradabad.

112 EWS HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 103 mo
137 NO SFS HOUSE IN SECT 14 OF MAJHOLA YOJ. NO 04 VISTAAR MORADABAD
UPRERA no delay on record
176 LIG HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 98 mo
2BHK (S+4) TYPE FLAT SECTOR-9A, MAJHOLA YOJNA-4, P
UPRERA ▲ 95 mo
32 MMIG HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 98 mo
59 NO SFS HOUS SEC 12A MAJHOLA YOJ 4 VISTAR MBD
UPRERA no delay on record

Common questions about 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR)

Is 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) RERA registered?

Yes. 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) is registered with UPRERA under registration number UPRERAPRJ13007, registered on 28 Sept 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Is 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) delayed?

48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) is 95 months past the completion date filed with UPRERA (3 Sept 2018), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is 48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) located?

48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR) is registered in Moradabad, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 95 mo
QPR filingNo default reported
DistrictMoradabad
Last updated4 Aug 2026

Location

AddressMoradabad
View on map ↗

RERA buyer helpline

Coordinator9927800728
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=KENjHADbAkA=&hfFlag=1E4qQMUGS4qnuSnOY2gD/g==&NPJ6RAme=o9rspCbxYaxIYm8fKlRxWg3xKI4sruynTwoVftReL5Lz7//z1C8A3ntzxAAt+lazbNlxx2ihZcQ=&PaURJEMAN4=ZL9MNERkNdarK1Ig40FpcA==&IRSAHEB=D6PY3lyims8=)