Registered11 Aug 2017
Promised15 Dec 2017
Completed2 Sept 2021

Timeline

Promised completion15 Dec 2017
Revised completion15 Dec 2017
Actual completion2 Sept 2021
Possession delay45 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,49,500
Project cost (in ₹ Lakhs)₹3,458.66 Lakhs
Project duration47 months
Project categoryResidential
Locality
Original start date16 Jan 2014
Proposed start date16 Jan 2014

Inventory

Total units896
Unit TypeUnitsCarpet Area (sqm)
1 BHK89629.7

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9711630738
Emailgdagzb@rediffmail.com
Coordinator9711364673
AddressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
GDA/Niyojan/146 Mar 20145 Mar 201915 Dec 20175 Mar 2022

Land Parcels

Khasra No.AreaPlot Type
PART - B LAYOUT INDRAPRASTH28850Khasra

Approved Unit Plan

Unit plan rows on file56
Total flats (sum of rows)896
BlocksTOWER 1, TOWER 10, TOWER 11, TOWER 12, TOWER 13, TOWER 14, TOWER 2, TOWER 3, TOWER 4, TOWER 5, TOWER 6, TOWER 7, TOWER 8, TOWER 9
Floor types1 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
ACQUIRED LAND11 Jun 1991

Frequently Asked Questions

What is the RERA registration number of 896 EWS houses (Four Storied) Indraprastha Awasyia?

The RERA registration number of 896 EWS houses (Four Storied) Indraprastha Awasyia is UPRERAPRJ6232, as recorded on the UP-RERA portal.

What is the RERA status of 896 EWS houses (Four Storied) Indraprastha Awasyia?

As reported by UP-RERA, the status of 896 EWS houses (Four Storied) Indraprastha Awasyia is "Registered".

Where is 896 EWS houses (Four Storied) Indraprastha Awasyia located?

As reported to UP-RERA, 896 EWS houses (Four Storied) Indraprastha Awasyia is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is 896 EWS houses (Four Storied) Indraprastha Awasyia completed?

As reported to UP-RERA, 896 EWS houses (Four Storied) Indraprastha Awasyia was completed on 2 Sept 2021.

Is 896 EWS houses (Four Storied) Indraprastha Awasyia delayed?

Measured against the latest completion date reported to UP-RERA, 896 EWS houses (Four Storied) Indraprastha Awasyia is 45 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.