Registered27 Jul 2017
Promised30 Jun 2019
Revised28 Jun 2020
Completed26 Sept 2023

Timeline

Promised completion30 Jun 2019
Revised completion28 Jun 2020
Actual completion26 Sept 2023
Possession delay39 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,05,000
Project cost (in ₹ Lakhs)₹32,400 Lakhs
Project duration87 months
Project categoryResidential
Locality
Original start date
Proposed start date13 Oct 2013

Inventory

Total units637
Unit TypeUnitsCarpet Area (sqm)
2 BHK31864.72–79.21
3 BHK31991.7–107

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8376804096
Emailinfo@aasthainfracity.com
Coordinator8376804095
AddressD 185 2ND FLOOR ASHOK VIHAR PHASE-1 DELHI-110052

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
I) PLG/(BP-3160/44/CPA-7027 DT 25.10.2013 2.) BP-

Revalidated: PLG/(BP), BP-3160/GH/FTS-3769 Dt. 02-07-2015 (2 Jul 2015)

25 Oct 201324 Oct 2018

Revalidated upto: 1 Jul 2020

28 Jun 20201 Jul 2020

Land Parcels

Khasra No.AreaPlot Type
GH-04SECTOR 4 GREATER NOIDA
3/GH-04, Sector 04,Greater Noida20000Plot

Approved Unit Plan

Unit plan rows on file80
Total flats (sum of rows)637
BlocksTOWER 1, TOWER 2, TOWER 3, TOWER 4
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
BAHI NO.1 JILD NO 12835 PAGE NO 183 TO 208 SL NO.621 Mar 2013
6616 page no. 183 to 208 jild no12835 bahi no.121 Mar 2013
6616 PAGE NO.183 TO 208 JILD NO.12835 BAHI NO.121 Mar 2013

Frequently Asked Questions

What is the RERA registration number of AASTHA GREENS?

The RERA registration number of AASTHA GREENS is UPRERAPRJ1050, as recorded on the UP-RERA portal.

What is the RERA status of AASTHA GREENS?

As reported by UP-RERA, the status of AASTHA GREENS is "Registered".

Where is AASTHA GREENS located?

As reported to UP-RERA, AASTHA GREENS is located at ITHARA, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is AASTHA GREENS completed?

As reported to UP-RERA, AASTHA GREENS was completed on 26 Sept 2023.

Is AASTHA GREENS delayed?

Measured against the latest completion date reported to UP-RERA, AASTHA GREENS is 39 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.