Timeline Bar

Registered14 Aug 2017
Promised31 Dec 2018
Completed12 Oct 2021

Timeline

Promised completion31 Dec 2018
Revised completion31 Dec 2018
Actual completion12 Oct 2021
Possession delay33 mo delay

Registration & Cost Details

Registration fee (in ₹)₹57,000
Project cost (in ₹ Lakhs)₹14,197 Lakhs
Project duration42 months
Project categoryResidential
Locality
Original start date27 Apr 2011
Proposed start date2 Jul 2015

Inventory

Total units457661
Unit TypeUnitsCarpet Area (sqm)
2 BHK30510157.2–61.51
3 BHK15256083.3

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8744000580
Emailaccounts@aimsgroup.in
Coordinator8130688334
Address3/10, Paschimi Marg, Vasant Vihar, New Delhi- 110057

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP).BP.2605/44/FIS-37682 Jul 20151 Jul 202031 Dec 20181 Jul 2020

Land Parcels

Khasra No.AreaPlot Type
nill0
GH 04136090.13Plot
GH 411462Plot

Approved Unit Plan

Unit plan rows on file480
Total flats (sum of rows)457661
BlocksA, B, C, D
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2452510 Dec 2010
672828 Feb 2014

Frequently Asked Questions

What is the RERA registration number of Aims Green Avenue (Phase-1)?

The RERA registration number of Aims Green Avenue (Phase-1) is UPRERAPRJ7473, as recorded on the UP-RERA portal.

What is the RERA status of Aims Green Avenue (Phase-1)?

As reported by UP-RERA, the status of Aims Green Avenue (Phase-1) is "Registered".

Where is Aims Green Avenue (Phase-1) located?

As reported to UP-RERA, Aims Green Avenue (Phase-1) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Aims Green Avenue (Phase-1) completed?

As reported to UP-RERA, Aims Green Avenue (Phase-1) was completed on 12 Oct 2021.

Is Aims Green Avenue (Phase-1) delayed?

Measured against the latest completion date reported to UP-RERA, Aims Green Avenue (Phase-1) is 33 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026