Estanzo

Timeline Bar

Registered30 Oct 2017
Promised5 May 2022
Today29 Jul 2026

Timeline

Promised completion5 May 2022
Revised completion5 May 2022
Actual completion
Possession delay51 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,95,000
Project cost (in ₹ Lakhs)₹2,508 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date27 Jan 2014
Proposed start date6 May 2017

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeIndividual
Mobile9455024525
Emailpuriamit42@gmail.com
Coordinator9455024525
Address39 Mahendri tola khairabad, sitapur.

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
28/anugya/ni.pra.vi.chha.c/17-186 May 20175 May 20225 May 20225 May 2025

Land Parcels

Khasra No.AreaPlot Type
11600 sqmtr
22410 sqmtr
31520 sqmtr
41520 sqmtr
51520 sqmtr
1113680 sqmtr
1311650 sqmtr
14350 sqmtr
15350 sqmtr
16350 sqmtr
17350 sqmtr
192230 sqmtr
256150 sqmtr
91690 sqmtr
2113380 sqmtr
23640 sqmtr
244450 sqmtr
315300 sqmtr
331300 sqmtr
23,2114020Khasra
9,24,31,3312740Khasra
256150Khasra
113420Khasra
14350Khasra
16350Khasra
17350Khasra
191115Khasra
15350Khasra
191115Khasra
116840Khasra
1311650Khasra
113420Khasra
1,2,3,4,58570Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
34672 Jun 2011
34682 Jun 2011
34712 Jun 2011
34692 Jun 2011
34702 Jun 2011
na5 Jun 2009
na5 Jun 2009
na5 Jun 2009
na8 Jul 2011
13481 Mar 2013
34652 Jun 2011
318824 May 2012
192710 Mar 2014
766923 Nov 2011

Frequently Asked Questions

What is the RERA registration number of Amit Puri?

The RERA registration number of Amit Puri is UPRERAPRJ14065, as recorded on the UP-RERA portal.

What is the RERA status of Amit Puri?

As reported by UP-RERA, the status of Amit Puri is "Registered".

Where is Amit Puri located?

As reported to UP-RERA, Amit Puri is located at Sitapur, Sitapur, Uttar Pradesh.

When will Amit Puri be completed?

The latest completion date reported to UP-RERA for Amit Puri is 5 May 2022.

Is Amit Puri delayed?

Measured against the latest completion date reported to UP-RERA, Amit Puri is 51 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026