ANSALS ELEGANCE TOWER C

UPRERAAbeyance

ANSALS ELEGANCE TOWER C is a RERA-registered residential project by Ansal Housing Limited in Ghaziabad (RERA ID UPRERAPRJ2538). RERA status: Abeyance.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Abeyance.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ2538
Project categoryResidential
Registration typeOngoing
RERA statusAbeyanceAbeyance“Held in suspension.” UP-RERA lists projects whose registration it has placed in abeyance.Read the full entry in the glossary
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBulandsahar Development Authority
Proposed start8 Apr 2015
Original start8 Apr 2015
Project duration69 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant address606, 6th Floor Indraprakash, 21 Barakhamba Road, New Delhi 110001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Registered with RERA

  3. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Abeyance. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Aug 2017
Original completion30 Jun 2020
Revised completion29 Dec 2020
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹17,500
Sanctioning authorityBulandsahar Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
NEERAJ KOCHER
License MCA/94/17709
D-330, GAUR GREEN AVENUE, ABHAY KHAND 2, PLOT NO. 1 AND 2 INDIARAPURAM, GZB-201014
Engineer
MAQSOOD E NAZAR
NNC DESIGN INTERNATIONAL, G-70, 2ND FLOOR, JASWANT PLAZA, OKHLA NEW DELHI-110025
Sr.Development work declared to RERA
1Demarcation of Plots
Done
2Boundary Wall
Completed
3Road Work
Pavered road
4Footpaths
Na
5Water Supply Including Drinking Water Facilities
Under ground water supply
6Sewer System
Under ground sewer system
7Drain
Underground drainage
8Parks
As per sanction
9Tree Planting
As per sancton
10Design For Electric Supply Including Street Lighting
Under ground electric cabling through dual meter supply.
11Community Buildings
Na
12Treatment and Disposal System of Sewage and Sullage water
STP as per sanction
13Solid Waste Management And Disposal System
Na
14Water Conservation System
Rain water harvesting
15Energy Management System Including Use of Renewable Energy
Use of led street lights
16Fire Protection And Fire Safety System
As per nbc
17Social Infrastructure And Other Public Amenities Including Public Health Services
Na
18Emergency Evacuation Services
As per nbc
19Other Miscellaneous Work
Na
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

0 permits

An approval and the date it runs to - not proof the work matching it was done.

Sanctioned by Bulandsahar Development Authority · 2,454 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Plans and approvals filed with RERA
DocumentFile
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 29 Dec 2020.

#Granted fromExtended uptoNote
130 Jun 202029 Dec 2020Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 1956
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2030-Part 1
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2030-Part 2
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2031-Part 1
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2031-Part 2
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2352-Part-1
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2352-Part-2
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3206
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New6 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New6 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New6 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old28 Jul 2017 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old28 Jul 2017 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old28 Jul 2017 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old28 Jul 2017 ↗

Quarterly progress reports

2 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

2 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q2.

QuarterConstructionCertificates
2020-Q1—Arch ↗ · Eng ↗
2020-Q2—Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAnsal Housing Limited
RolePromoter · current
RERA IDUPRERAPRM450
PANAAACA0377R
CIN / TANDELA12078D
Name of chairmanDeepak Ansal
Registered address606, 6th Floor Indraprakash, 21 Barakhamba Road, New Delhi 110001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

5 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No project bank account is published for this project.Ask which RERA-designated account payments are to be made to, and check the details against the UP-RERA page before paying anything.
  • No khasra or plot detail is published for this project.Ask which khasra numbers the project stands on, so the plot can be matched against the deed and the revenue record.
  • No sanctioning permit is published for this project.Ask which authority sanctioned the plans, for the permit number, and for the date it is valid to.
  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ANSALS ELEGANCE TOWER C

Is ANSALS ELEGANCE TOWER C RERA registered?

Yes. ANSALS ELEGANCE TOWER C is registered with UPRERA under registration number UPRERAPRJ2538, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ANSALS ELEGANCE TOWER C?

The completion date filed with UPRERA is 29 Dec 2020. No completion certificate is on record yet.

Who is the builder of ANSALS ELEGANCE TOWER C?

Ansal Housing Limited is the promoter entity that filed ANSALS ELEGANCE TOWER C with UPRERA (promoter RERA ID UPRERAPRM450). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted ANSALS ELEGANCE TOWER C more time to complete?

UPRERA's record carries 1 completion extension for ANSALS ELEGANCE TOWER C, the latest running to 29 Dec 2020. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Where is ANSALS ELEGANCE TOWER C located?

ANSALS ELEGANCE TOWER C is registered in Ghaziabad, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗