Registered6 Jan 2020
Promised17 Dec 2024
Today4 Aug 2026

Timeline

Promised completion17 Dec 2024
Revised completion17 Dec 2024
Actual completion
Possession delay20 mo delay

Registration & Cost Details

Registration fee (in ₹)₹88,000
Project cost (in ₹ Lakhs)₹57,500 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jul 2020

Inventory

Total units340
Unit TypeUnitsCarpet Area (sqm)
2 BHK11278.87–82.68
3 BHK228122.82–166.67

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9873707675
Emailcontactus@antaranoida.com
Coordinator9810402975
AddressDGL006, Ground Floor, DLF Galleria, Mayur Vihar, Phase-I, New Delhi-110091

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/MVN/2019/IV-1532/115718 Dec 201917 Dec 202417 Dec 202417 Dec 2027

Revalidated: NOIDA/MVN/2019/IV-1532/1157 (18 Dec 2019)

1 Jan 190017 Dec 2024

Revalidated upto: 17 Dec 2024

17 Dec 202417 Dec 2027

Land Parcels

Khasra No.AreaPlot Type
SC-01/B-1 SECTOR 150 NOIDA32372.90Plot

Approved Unit Plan

Unit plan rows on file154
Total flats (sum of rows)340
BlocksRESIDENCE 1, RESIDENCE 2, RESIDENCE 3
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of ANTARA NOIDA PHASE 1?

The RERA registration number of ANTARA NOIDA PHASE 1 is UPRERAPRJ745377, as recorded on the UP-RERA portal.

What is the RERA status of ANTARA NOIDA PHASE 1?

As reported by UP-RERA, the status of ANTARA NOIDA PHASE 1 is "Registered".

Where is ANTARA NOIDA PHASE 1 located?

As reported to UP-RERA, ANTARA NOIDA PHASE 1 is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will ANTARA NOIDA PHASE 1 be completed?

The latest completion date reported to UP-RERA for ANTARA NOIDA PHASE 1 is 17 Dec 2024.

Is ANTARA NOIDA PHASE 1 delayed?

Measured against the latest completion date reported to UP-RERA, ANTARA NOIDA PHASE 1 is 20 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.