Timeline Bar

Registered14 Aug 2017
Promised12 Sept 2018
Completed23 Jun 2020

Timeline

Promised completion12 Sept 2018
Revised completion12 Sept 2018
Actual completion23 Jun 2020
Possession delay21 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,38,500
Project cost (in ₹ Lakhs)₹66,119 Lakhs
Project duration96 months
Project categoryResidential
Locality
Original start date13 Sept 2010
Proposed start date13 Sept 2010

Inventory

Total units1597
Unit TypeUnitsCarpet Area (sqm)
2 BHK90857.16–210.77
3 BHK59416.722–228.162
4 BHK82143.223–199.104
PENTHOUSE13172.059–371.612

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310068117
Emailrera.golfview1@hotmail.com
Coordinator9310836617
Address34/C-8, SECTOR-8, ROHINI, NEW DELHI-110085

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
34819 Jul 201618 Jul 202112 Sept 201818 Jul 2026

Land Parcels

Khasra No.AreaPlot Type
Plot No. GH 005A49918.95
GH-005A49918.95Plot

Approved Unit Plan

Unit plan rows on file961
Total flats (sum of rows)1597
BlocksA, B, C, D, E, F, G, H, J, K, L, M, N, P, R
Floor types2 BHK, 3 BHK, 4 BHK, PENTHOUSE

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
39354 Jun 2010

Frequently Asked Questions

What is the RERA registration number of Antriksh Golf View I?

The RERA registration number of Antriksh Golf View I is UPRERAPRJ10343, as recorded on the UP-RERA portal.

What is the RERA status of Antriksh Golf View I?

As reported by UP-RERA, the status of Antriksh Golf View I is "Registered".

Where is Antriksh Golf View I located?

As reported to UP-RERA, Antriksh Golf View I is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Antriksh Golf View I completed?

As reported to UP-RERA, Antriksh Golf View I was completed on 23 Jun 2020.

Is Antriksh Golf View I delayed?

Measured against the latest completion date reported to UP-RERA, Antriksh Golf View I is 21 months beyond that date.