Registered14 Aug 2017
Promised1 Dec 2017
Completed28 May 2019

Timeline

Promised completion1 Dec 2017
Revised completion1 Dec 2017
Actual completion28 May 2019
Possession delay18 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,59,000
Project cost (in ₹ Lakhs)₹42,800 Lakhs
Project duration83 months
Project categoryResidential
Locality
Original start date1 Feb 2011
Proposed start date1 Feb 2011

Inventory

Total units917
Unit TypeUnitsCarpet Area (sqm)
1 BHK649.375–73.65
2 BHK39157.07–70.49
3 BHK51278.05–91.4
SHOP829.75–39.08

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9999967463
Emailrera@colorfulestates.com
Coordinator9999967463
AddressR-3/109, NAWADA HOUSING COMPLEX, UTTAM NAGAR, NEW DELHI-110059

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
?????/ ???0 ?0 ??0 / III -240/3341 Feb 201130 Jan 20161 Dec 201730 Jan 2018

Land Parcels

Khasra No.AreaPlot Type
Plot No. GH-04/BSector-78, Noida
GH-04B30797Plot

Approved Unit Plan

Unit plan rows on file259
Total flats (sum of rows)917
Total shops8
BlocksB, D, E, F, G, H, J, K, L, M
Floor types1 BHK, 2 BHK, 3 BHK, SHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
546412 Aug 2010

Frequently Asked Questions

What is the RERA registration number of Antriksh Golf View II - Phase I?

The RERA registration number of Antriksh Golf View II - Phase I is UPRERAPRJ10857, as recorded on the UP-RERA portal.

What is the RERA status of Antriksh Golf View II - Phase I?

As reported by UP-RERA, the status of Antriksh Golf View II - Phase I is "Registered".

Where is Antriksh Golf View II - Phase I located?

As reported to UP-RERA, Antriksh Golf View II - Phase I is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Antriksh Golf View II - Phase I completed?

As reported to UP-RERA, Antriksh Golf View II - Phase I was completed on 28 May 2019.

Is Antriksh Golf View II - Phase I delayed?

Measured against the latest completion date reported to UP-RERA, Antriksh Golf View II - Phase I is 18 months beyond that date.