Timeline Bar
Registered15 Aug 2017
Promised30 Dec 2019
Completed15 Sept 2023
Timeline
Promised completion30 Dec 2019
Revised completion30 Dec 2019
Actual completion15 Sept 2023
Possession delay45 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,08,500
Project cost (in ₹ Lakhs)₹2,000 Lakhs
Project duration49 months
Project categoryResidential
Locality—
Original start date1 Mar 2011
Proposed start date4 Dec 2015
Inventory
Total units616
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 48 | 32.51 |
| 2 BHK | 105 | 42–82 |
| 3 BHK | 194 | 90–112 |
| 4 BHK | 166 | 110.72–162 |
| 5 BHK | 76 | 174 |
| SHOP | 27 | 31 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8510042211
Emailorchard.avs4@gmail.com
Coordinator9810298653
AddressGH 03C ,SECTOT-77,Noida
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| III-226 | 26 Nov 2013 | 26 Nov 2018 | 30 Dec 2019 | 26 Nov 2021 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| GHO3C, SECTOR-77, NOIDA | 20700 | — |
Approved Unit Plan
Unit plan rows on file24
Total flats (sum of rows)616
Total shops27
BlocksA, B, C, D, E, F, G, SHOP/ COMMERCIAL
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, 5 BHK, SHOP
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| BOOK NO.1,JILD NO. 1897,PAGE NO. 187 TO 228,SERIAL | 22 Jul 2010 | — | — |
Frequently Asked Questions
What is the RERA registration number of AVS ORCHARD?
The RERA registration number of AVS ORCHARD is UPRERAPRJ7336, as recorded on the UP-RERA portal.
What is the RERA status of AVS ORCHARD?
As reported by UP-RERA, the status of AVS ORCHARD is "Registered".
Where is AVS ORCHARD located?
As reported to UP-RERA, AVS ORCHARD is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.
Is AVS ORCHARD completed?
As reported to UP-RERA, AVS ORCHARD was completed on 15 Sept 2023.
Is AVS ORCHARD delayed?
Measured against the latest completion date reported to UP-RERA, AVS ORCHARD is 45 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026