Timeline Bar
Registered10 Aug 2017
Promised31 Mar 2018
Today4 Aug 2026
Timeline
Promised completion31 Mar 2018
Revised completion31 Mar 2018
Actual completion—
Possession delay100 mo delay
Registration & Cost Details
Registration fee (in ₹)₹62,000
Project cost (in ₹ Lakhs)₹450 Lakhs
Project duration36 months
Project categoryResidential
Locality—
Original start date25 Apr 2015
Proposed start date25 Apr 2015
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9837038608
Emailbanarsidassestate@gmail.com
Coordinator9837038608
AddressKHASARA NO. 1049, MALIYANA NEAR-BAGHPAT ROAD RAILWAY OVER BRIDGE ,MEERUT
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 41/14 | 8 Jan 2016 | 7 Jan 2021 | 31 Mar 2018 | 7 Jan 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1408 | 11375 | — |
Frequently Asked Questions
What is the RERA registration number of BANARSI DASS ESTATE?
The RERA registration number of BANARSI DASS ESTATE is UPRERAPRJ8959, as recorded on the UP-RERA portal.
What is the RERA status of BANARSI DASS ESTATE?
As reported by UP-RERA, the status of BANARSI DASS ESTATE is "Registered".
Where is BANARSI DASS ESTATE located?
As reported to UP-RERA, BANARSI DASS ESTATE is located at Meerut, Meerut, Uttar Pradesh.
When will BANARSI DASS ESTATE be completed?
The latest completion date reported to UP-RERA for BANARSI DASS ESTATE is 31 Mar 2018.
Is BANARSI DASS ESTATE delayed?
Measured against the latest completion date reported to UP-RERA, BANARSI DASS ESTATE is 100 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026