Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ14205
Project categoryResidential
Registration typeOngoing
RERA statusCompleted
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Sept 2012
Original start1 Sept 2012
Project duration112 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressSHOP NO-07, RBI COLONY MARKET, HAUZ KHAS, NEW DELHI- 110016
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated

    BP/697/IT/10823

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. valid to

    Permit revalidated

    PLG/(BP)/697(S)/2019/6090

  6. to

    Extension granted

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  9. to

    Extension granted

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  11. Completion certificate filed

  12. Completion certificate filed

Published without a date
UPRERA lists this project as Completed.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Oct 2017
Original completion31 Dec 2019
Revised completion28 Mar 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary28 Nov 2025
Registration fee₹39,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors397 · 2 · 15 (units from plan)
  • STUDIO248 62%
  • 1 BHK149 38%
ConfigurationUnitsCarpet area
1 BHK14931-35
STUDIO24820-20
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER A · 1 BHK, STUDIO1526220-35
TOWER B · 1 BHK1513531-34
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MODARCH INDIA
License CA/98/22706
B-99, 1st FLOOR,SECTOR 63, NOIDA -201301
Engineer
D&R CONSULTANTS
100, 3rd FLOOR , BHARAT NAGAR ,NFC, NEW DELHI
Contractor
ANSAR INDIA INFRATECH PRIVATE LIMITED
K-319, NAI BASTI,NEW SILAMPUR, NEW DELHI-110053
Sr.Development work declared to RERA
1Demarcation of Plots
AS PER PLAN
2Boundary Wall
AS PER PLAN
3Road Work
AS PER PLAN
4Footpaths
AS PER PLAN
5Water Supply Including Drinking Water Facilities
Source of water shall be primarily through proposed tube wells .RO unit is proposed in each flat
6Sewer System
Soil & Waste from Toilet & Kitchen will be collected separately for soil & waster pipe line and after that sewer pipe line laid under ground( NP-2) with manhole & connected proposed STP
7Drain
Separate line for rain water with & Other line for soil & waste and connected to STP
8Parks
AS PER PLAN
9Tree Planting
AS PER PLAN
10Design For Electric Supply Including Street Lighting
Efficient & Effective design of substation with 100% Power back up & street light in walk way and parks . Adequate design to reduce losses in transmission & distribution .
11Community Buildings
AS PER PLAN
12Treatment and Disposal System of Sewage and Sullage water
Sewer water treatment through STP with their disposal arrangement
13Solid Waste Management And Disposal System
AS PER PLAN
14Water Conservation System
Energy efficient pumps used with sensor , treated STP water used for flushing & Horticulture
15Energy Management System Including Use of Renewable Energy
Pumps & equipment selected on best energy efficient point . Photoelectric senor used for external and common area light with provision of solar energy
16Fire Protection And Fire Safety System
Internal & external hydrant system , Basement sprinkler ,MCP & Fire Extinguishers in all floors . As per Fire norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
AS PER PLAN
18Emergency Evacuation Services
AS PER PLAN
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1Earth Homes Pvt. LtdUPRERAAGT11244
2INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 1 Dec 2016. 2 of them carry a revalidation, the latest valid to 1 Dec 2021.

Sanctioned by Greater Noida Authority · 6,706 sqm of land · an approved plan of 2 blocks and 397 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
BP/697/IT/108232 Dec 20111 Dec 20161 Dec 202128 Mar 2022—
BP/697/IT/108232 Dec 20111 Dec 20161 Dec 202128 Mar 202218 Sept 2019
valid to 1 Dec 2021
as PLG/(BP)/697(S)/2019/6090
BP/697/IT/108232 Dec 20111 Dec 20161 Dec 20211 Dec 20212 Dec 2011
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Mar 2022.

#Granted fromExtended uptoNote
131 Dec 201930 Dec 2020—
230 Dec 202029 Jun 2021Six months extension in view of force majeure caused by covid-19 pandemic
329 Jun 202128 Mar 2022—

Land & documents

6 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
plot no 216706—
21K P-036706Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 20 Mar 2002.

Registry no.DateTypeArea
154720 Mar 2002self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 1547
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old31 Oct 2017 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameYuvraj Infra Venture Private Limited
RolePromoter · current
RERA IDUPRERAPRM29044
PANAAACY5686K
CIN / TANU70102DL2012PTC241881
Name of chairmanMOHD IRSHAD
Registered addressSHOP NO-07, RBI COLONY MARKET, HAUZ KHAS, NEW DELHI- 110016
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
CURRENT ACCOUNTBankAXIS BANK LTDBranchNOIDAA/C no.IFSCUTIB000361
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

4 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)66 (Under Registration - 2 ) → 66 (Under Registration - 1 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)65 (Under Registration - 1 ) → 66 (Under Registration - 2 )
changed in Estanzo’s record
7 Oct 2026
Promoter’s complaints tally (all their projects)64 (Under Registration - 0 ) → 65 (Under Registration - 1 )
changed in Estanzo’s record
15 Sept 2026
Promoter’s complaints tally (all their projects)64 (Under Registration - 1 ) → 64 (Under Registration - 0 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 4 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about BEETLE ORCHID

Is BEETLE ORCHID RERA registered?

Yes. BEETLE ORCHID is registered with UPRERA under registration number UPRERAPRJ14205, registered on 31 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has BEETLE ORCHID been completed?

UPRERA lists BEETLE ORCHID as completed, with a completion certificate dated 28 Nov 2025, against a filed deadline of 28 Mar 2022.

Who is the builder of BEETLE ORCHID?

Yuvraj Infra Venture Private Limited is the promoter entity that filed BEETLE ORCHID with UPRERA (promoter RERA ID UPRERAPRM29044). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted BEETLE ORCHID more time to complete?

UPRERA's record carries 3 completion extensions for BEETLE ORCHID, the latest running to 28 Mar 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does BEETLE ORCHID have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is BEETLE ORCHID located?

BEETLE ORCHID is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in BEETLE ORCHID?

The unit plan filed with UPRERA lists 1 BHK and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in BEETLE ORCHID?

The approved unit plan filed with UPRERA runs from 20 to 35 m² of carpet area (about 210 to 374 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in BEETLE ORCHID?

The approved unit plan describes 2 blocks and 397 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is BEETLE ORCHID?

About 240 units per acre: 397 planned units across 1.66 acres (6,706 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗