Buildia Galaxy is a RERA-registered residential project by BUILDIA CONSTRUCTION PRIVATE LIMITED in Lucknow (RERA ID UPRERAPRJ12630). Registered with a completion deadline of 28 Dec 2021.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ12630 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Any Other Competent Authority |
| Proposed start | 1 Dec 2015 |
| Original start | 1 Dec 2015 |
| Project duration | 58 months |
| Address | Bakshi Ka Talab**, Lucknow |
| Tehsil | Bakshi Ka Talab** |
| Applicant type | Company |
| Applicant address | SEDARPUR, KARORA, GOSAIGANJ, LUCKNOW- 227125 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated (2)
2 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 31 Oct 2017 |
| Original completion | 31 Dec 2019 |
| Revised completion | 28 Dec 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 10 Mar 2026 |
| Registration fee | ₹17,500 |
| Sanctioning authority | Any Other Competent Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK37 51%
- 1 BHK23 32%
- 3 BHK12 17%
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 12 | 101 |
| 2 BHK | 37 | 59-87 |
| 1 BHK | 23 | 59-60 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| BUILDIA GALAXY · 3 BHK, 2 BHK, 1 BHK, OTHER | 7 | 72 | 59-101 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 21 Sept 2020. All 2 carry a revalidation, the latest valid to 21 Sept 2020.
Sanctioned by Any Other Competent Authority · an approved plan of 1 block and 72 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 994 | 29 Oct 2015 | 21 Sept 2020 | 26 Sept 2024 | 15 Sept 2020 | 29 Oct 2015 valid to 21 Sept 2020 | |
| 994 | 29 Oct 2015 | 21 Sept 2020 | 26 Sept 2024 | 15 Sept 2020 | 29 Oct 2015 valid to 21 Sept 2020 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Dec 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Dec 2019 | 30 Dec 2020 | — |
| 2 | 30 Dec 2020 | 29 Jun 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 3 | 29 Jun 2021 | 28 Dec 2021 | — |
Land & documents
3 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 224 and 497 ka | 25859 sqft | — |
| 224 AND 497 KA | 2402.359 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 31 Aug 2015.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 11310 | 31 Aug 2015 | other | — |
| Registry document · IN-UP01296411440396N The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · IN-UP01296411440396N The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 31 Oct 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | yes |
| Fire safety (as filed with RERA) | applied for |
| Health service | no |
| Renewable energy | no |
| Other facilities | no |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | BUILDIA CONSTRUCTION PRIVATE LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM24003 |
| PAN | AAFCB8558C |
| CIN / TAN | LKON11111F |
| Name of chairman | MOHD MOAZZAM |
| Registered address | SEDARPUR, KARORA, GOSAIGANJ, LUCKNOW- 227125 |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | BUILDIA CONSTRUCTION PVT LTDBankICICI BANKBranchLEKHRAJ PANNA MARKETA/C no.IFSCICIC0006959 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
Common questions about Buildia Galaxy
Is Buildia Galaxy RERA registered?
Yes. Buildia Galaxy is registered with UPRERA under registration number UPRERAPRJ12630, registered on 31 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has Buildia Galaxy been completed?
UPRERA still lists Buildia Galaxy as Registered, so it is not shown as completed here. A completion certificate dated 10 Mar 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of Buildia Galaxy?
BUILDIA CONSTRUCTION PRIVATE LIMITED is the promoter entity that filed Buildia Galaxy with UPRERA (promoter RERA ID UPRERAPRM24003). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Buildia Galaxy more time to complete?
UPRERA's record carries 3 completion extensions for Buildia Galaxy, the latest running to 28 Dec 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Buildia Galaxy have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Buildia Galaxy located?
Buildia Galaxy is registered in Lucknow, as filed with UPRERA.
What configurations are available in Buildia Galaxy?
The unit plan filed with UPRERA lists 3 BHK, 2 BHK, 1 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Buildia Galaxy?
The approved unit plan filed with UPRERA runs from 59 to 101 m² of carpet area (about 640 to 1,090 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Buildia Galaxy?
The approved unit plan describes 1 block and 72 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗