Timeline Bar

Registered12 Aug 2017
Promised30 Jun 2020
Revised28 Sept 2022
Completed11 Sept 2023

Timeline

Promised completion30 Jun 2020
Revised completion28 Sept 2022
Actual completion11 Sept 2023
Possession delay11 mo delay

Registration & Cost Details

Registration fee (in ₹)₹46,500
Project cost (in ₹ Lakhs)₹14,658 Lakhs
Project duration116 months
Project categoryResidential
Locality
Original start date27 Feb 2013
Proposed start date27 Feb 2013

Inventory

Total units434
Unit TypeUnitsCarpet Area (sqm)
2 BHK27357.418–66.84
3 BHK16173.268–105.267

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9311606012
Emailinfo@capitalathena.com
Coordinator9873366777
AddressPLOT NO- GH-12A-2, SECTOR-01, GREATER NOIDA (WEST), GAUTAM BUDH NAGAR, U.P.-201306

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP)BP3090/GH/PA-137427 Feb 201327 Feb 201828 Sept 202227 Feb 2023
PLG/BP)BP3090/GH/PA-137427 Feb 201326 Feb 201828 Sept 202226 Feb 2023
PLG/BP)BP3090/GH/PA-137427 Feb 201326 Feb 201828 Sept 202227 Feb 2023

Land Parcels

Khasra No.AreaPlot Type
gfhfjkggfhfj
GH12A-233941.79Plot

Approved Unit Plan

Unit plan rows on file221
Total flats (sum of rows)434
Blocks6, 7, 8
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2258922 Nov 2012

Frequently Asked Questions

What is the RERA registration number of Capital Athena (Phase-1)?

The RERA registration number of Capital Athena (Phase-1) is UPRERAPRJ6310, as recorded on the UP-RERA portal.

What is the RERA status of Capital Athena (Phase-1)?

As reported by UP-RERA, the status of Capital Athena (Phase-1) is "Registered".

Where is Capital Athena (Phase-1) located?

As reported to UP-RERA, Capital Athena (Phase-1) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Capital Athena (Phase-1) completed?

As reported to UP-RERA, Capital Athena (Phase-1) was completed on 11 Sept 2023.

Is Capital Athena (Phase-1) delayed?

Measured against the latest completion date reported to UP-RERA, Capital Athena (Phase-1) is 11 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026