Estanzo

Timeline Bar

Registered14 Oct 2021
Promised4 Jul 2026
Today29 Jul 2026

Timeline

Promised completion4 Jul 2026
Revised completion4 Jul 2026
Actual completion
Possession delay1 mo delay

Registration & Cost Details

Registration fee (in ₹)₹4,10,000
Project cost (in ₹ Lakhs)₹32,542 Lakhs
Project duration58 months
Project categoryCommercial
Locality
Original start date
Proposed start date27 Sept 2021

Inventory

Total units1060
Unit TypeUnitsCarpet Area (sqm)
OTHER10607.08–242.4

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9811078090
Emailanandhabitatinfra@gmail.com
Coordinator9650989219
AddressC-60 1ST FLOOR DOUBLE STOREY RAMESH NAGAR DELHI West Delhi DL 110015

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q20.0%
2025-Q30.0%
2025-Q479.3%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/BC/BP/V-556/7065 Jul 20214 Jul 20264 Jul 20263 Jul 2030

Land Parcels

Khasra No.AreaPlot Type
A-37,3840000Plot

Approved Unit Plan

Unit plan rows on file236
Total flats (sum of rows)1060
BlocksA
Floor typesOTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Capitol Avenue?

The RERA registration number of Capitol Avenue is UPRERAPRJ665479, as recorded on the UP-RERA portal.

What is the RERA status of Capitol Avenue?

As reported by UP-RERA, the status of Capitol Avenue is "Registered".

Where is Capitol Avenue located?

As reported to UP-RERA, Capitol Avenue is located at (IT/ITES) Plot No. A-37 & A-38, Noida Sector - 62, Gautam Buddha Nagar, Uttar Pradesh - 201301, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Capitol Avenue be completed?

The latest completion date reported to UP-RERA for Capitol Avenue is 4 Jul 2026.

Is Capitol Avenue delayed?

Measured against the latest completion date reported to UP-RERA, Capitol Avenue is 1 month beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.