Central Avenue

UPRERARegistered

Central Avenue is a RERA-registered commercial project by ASR REALTECH LTD in Ghaziabad (RERA ID UPRERAPRJ658066). Registered with a completion deadline of 28 May 2026. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
74%Q2'25
74%Q3'25
74.97%Q4'25
76%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ658066
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start28 May 2023
Project duration37 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressF-93A, GALI NO-07 JAGATPURI DELHI-110051
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Hotel/02947/GDA/BP/20-21/1087/14042022

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered9 Oct 2023
Original completion28 May 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹36,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors124 · 1 · 9 (units from plan)
Homes · commercial units73 · 51 (shops and offices filed in the same plan)
  • OTHER73 59%
  • SHOP51 41%
ConfigurationUnitsCarpet area
SHOP5120-26
OTHER7329-187
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Central Avenue · SHOP, OTHER912420-187
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 109.95 m² for a SHOP, 722.79 m² for a OTHER, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Abhishek Singh
License CA/2013/60896
H.No-587 Block-C Panki , Kanpur Nagar (UP) - 208020
Engineer
Rabi Aktar
2nd Floor, 212, Aravali Apartment, Gali No- 7 Gaffar Manzil, Jamia Nagar okhla, South Delhi- 110025
Contractor
M s Swastik Engg Builders
A-219 , Bhopra Defence Colony Sahiabad, Ghaziabad (UP) -201005
Sr.Development work declared to RERA
1Demarcation of Plots
Not Applicable
2Boundary Wall
Consisting height (7FT) Consisting of Rcc And Brick work
3Road Work
All roads in the complex will be in combination of concrete pavers of different colours, shape thickness Road will be laid over 225mm water bound macadam.
4Footpaths
All footpath in the complex will be in combination of concrete pavers of different colours, shape thickness of 65 mm and 80mm laid over 150mm water bound macadam surface.
5Water Supply Including Drinking Water Facilities
Potable water supply from municipal water supply shall be collected in underground collection tank and pumped to overhead water tank . The supply of water to individual Units shall be from the said overhead water tanks.
6Sewer System
The sewage will be collected through a soil pipeline arrangement bends and inspection chambers leading to the sewage water treatment plant (STP) of the project and treated water will be used for irrigation and flushing purpose.
7Drain
Drains having a minimum width of 150 mm will be provided for collection and channelization of rain water (surface run off).
8Parks
Hard and soft landscape is done in park with electrical lighting .
9Tree Planting
The tress will be planted at all suitable location of the project and along the boundary walls. The tree ,selection flora and vegetation shall be as per the climatic conditions. Tress will be planted in a manner to ensure that there is no hindrance in the services / usage in the project.
10Design For Electric Supply Including Street Lighting
Street light is directly operated bt solar panel installed on top floor of the building .
11Community Buildings
Community building is not required on site as per GDA norms .
12Treatment and Disposal System of Sewage and Sullage water
Sewage shall be treated in sewage Treatment plant (STP) and there after treated water to be used for flushing and irrigation.
13Solid Waste Management And Disposal System
Solid waste to be collected from individual flats and stored in garbage room. Recyclable shall be processed in the compost machine to make compost. Non recyclable waste shall be disposed of through approved agents.
14Water Conservation System
Rain water harvesting pits shall be provided for ground water recharging and overflow to be discharged in the municipal drains. Treated sewage shall be used for irrigation and flushing.
15Energy Management System Including Use of Renewable Energy
Solar plant will be installed on top for conservation of electricity .
16Fire Protection And Fire Safety System
Sprinkler, fire doors, yard hydrants, smoke detector and fire alarm system will be provided as applicable.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Fire tower is designed for evacuation services in building .
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 12 Apr 2028.

Sanctioned by Ghaziabad Development Authority · 2,569 sqm of land · an approved plan of 1 block and 124 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Hotel/02947/GDA/BP/20-21/1087/1404202213 Apr 202312 Apr 202812 Apr 203128 May 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1067 and 10682569Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 176
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
General body resolution
The resolution authorising an apartment owners’ association to act as the registering entity.
not reported—
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New9 Aug 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New9 Aug 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New9 Aug 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New9 Aug 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New9 Aug 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New9 Aug 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New9 Aug 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New9 Aug 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Sept 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New9 Aug 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New9 Aug 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New9 Aug 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New6 Sept 2023 ↗

Quarterly progress reports

12 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

12 quarterly progress reports are on file with UPRERA, covering 2023-Q1 to 2025-Q4.

QuarterConstructionCertificates
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q174%CA ↗ · Arch ↗ · Eng ↗
2025-Q274%CA ↗ · Arch ↗ · Eng ↗
2025-Q374.97%CA ↗ · Arch ↗ · Eng ↗
2025-Q476%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameASR REALTECH LTD
RolePromoter · current
RERA IDUPRERAPRM237381
PANAABCN8169P
CIN / TANDELN05323D
Name of chairmanSandeep Kumar
Registered addressF-93A, GALI NO-07 JAGATPURI DELHI-110051
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
ASR REALTECH LIMITED COLLECTION ACCOUNT FOR CENTRAL AVENUEBankAxis BankBranchRDC Raj NagarBranch addressRDC Raj Nagar GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001082
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
ASR REALTECH LIMITED SEPARATE ACCOUNT FOR CENTRAL AVENUEBankAxis BankBranchRDC Raj NagarBranch addressRDC Raj Nagar GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001082
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
ASR REALTECH LIMITED RERA TRANSACTION ACCOUNT FOR CENTRAL AVENUEBankAxis BankBranchRDC Raj NagarBranch addressRDC Raj Nagar GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001082
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)1 (Under Registration - 1 ) → 1 (Under Registration - 0 )
changed in Estanzo’s record
25 Sept 2026
Default-on-QPR flagfalse → true
changed in Estanzo’s record
31 Aug 2026
Promoter’s complaints tally (all their projects)0 (Under Registration - 0 ) → 1 (Under Registration - 1 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 25 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Central Avenue

Is Central Avenue RERA registered?

Yes. Central Avenue is registered with UPRERA under registration number UPRERAPRJ658066, registered on 9 Oct 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Central Avenue?

The completion date filed with UPRERA is 28 May 2026. No completion certificate is on record yet.

Who is the builder of Central Avenue?

ASR REALTECH LTD is the promoter entity that filed Central Avenue with UPRERA (promoter RERA ID UPRERAPRM237381). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does Central Avenue show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Does Central Avenue have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Central Avenue located?

Central Avenue is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in Central Avenue?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Central Avenue?

The approved unit plan filed with UPRERA runs from 20 to 187 m² of carpet area (about 215 to 2,010 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Central Avenue?

The approved unit plan describes 1 block and 124 units of which 73 are homes and 51 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Central Avenue?

About 195 units per acre: 124 planned units across 0.63 acres (2,569 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗