Estanzo

Timeline Bar

Registered11 Aug 2017
Promised31 Dec 2018
Revised30 Jun 2019
Completed18 Sept 2019

Timeline

Promised completion31 Dec 2018
Revised completion30 Jun 2019
Actual completion18 Sept 2019
Possession delay3 mo delay

Registration & Cost Details

Registration fee (in ₹)₹27,000
Project cost (in ₹ Lakhs)₹2,792 Lakhs
Project duration54 months
Project categoryResidential
Locality
Original start date7 Jan 2015
Proposed start date7 Jan 2015

Inventory

Total units120
Unit TypeUnitsCarpet Area (sqm)
2 BHK12052.3

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9711630738
Emailgdagzb@rediffmail.com
Coordinator8373916794
AddressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
597/MAP/01/03/20145 Apr 201412 Jan 201930 Jun 201930 Jun 2019

Land Parcels

Khasra No.AreaPlot Type
PART OF KHASRA NO. 961,962 & 701 OF REVENUE VILLAG4375 SQM
961,962 & 7014375Khasra

Approved Unit Plan

Unit plan rows on file12
Total flats (sum of rows)120
BlocksTOWER 1
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NA10 Aug 2017

Frequently Asked Questions

What is the RERA registration number of Construction of 120 multi storey houses Chandrashi?

The RERA registration number of Construction of 120 multi storey houses Chandrashi is UPRERAPRJ6266, as recorded on the UP-RERA portal.

What is the RERA status of Construction of 120 multi storey houses Chandrashi?

As reported by UP-RERA, the status of Construction of 120 multi storey houses Chandrashi is "Registered".

Where is Construction of 120 multi storey houses Chandrashi located?

As reported to UP-RERA, Construction of 120 multi storey houses Chandrashi is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is Construction of 120 multi storey houses Chandrashi completed?

As reported to UP-RERA, Construction of 120 multi storey houses Chandrashi was completed on 18 Sept 2019.

Is Construction of 120 multi storey houses Chandrashi delayed?

Measured against the latest completion date reported to UP-RERA, Construction of 120 multi storey houses Chandrashi is 3 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.