Registered2 Aug 2017
Promised14 Apr 2018
Completed1 Oct 2019

Timeline

Promised completion14 Apr 2018
Revised completion14 Apr 2018
Actual completion1 Oct 2019
Possession delay18 mo delay

Registration & Cost Details

Registration fee (in ₹)₹39,500
Project cost (in ₹ Lakhs)₹4,038.5 Lakhs
Project duration21 months
Project categoryResidential
Locality
Original start date15 Jul 2016
Proposed start date15 Jul 2016

Inventory

Total units259
Unit TypeUnitsCarpet Area (sqm)
2 BHK25951.27

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9711630738
Emailgdagzb@rediffmail.com
Coordinator9711364673
AddressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
678/NEYO-ANU/201628 Apr 201613 Jan 201914 Apr 201830 Jun 2019

Land Parcels

Khasra No.AreaPlot Type
431MI, 446MI6821Khasra

Approved Unit Plan

Unit plan rows on file27
Total flats (sum of rows)259
BlocksTOWER A, TOWER B, TOWER C
Floor types2 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of construction of 259 multi storied flat at GH-9?

The RERA registration number of construction of 259 multi storied flat at GH-9 is UPRERAPRJ6013, as recorded on the UP-RERA portal.

What is the RERA status of construction of 259 multi storied flat at GH-9?

As reported by UP-RERA, the status of construction of 259 multi storied flat at GH-9 is "Registered".

Where is construction of 259 multi storied flat at GH-9 located?

As reported to UP-RERA, construction of 259 multi storied flat at GH-9 is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is construction of 259 multi storied flat at GH-9 completed?

As reported to UP-RERA, construction of 259 multi storied flat at GH-9 was completed on 1 Oct 2019.

Is construction of 259 multi storied flat at GH-9 delayed?

Measured against the latest completion date reported to UP-RERA, construction of 259 multi storied flat at GH-9 is 18 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026