Construction of 384 EWS Houses under PMAY (Urban) Scheme at Lakri Fazalpur Gata No. 2407/1, Moradabad is a RERA-registered real-estate project in Moradabad (RERA ID UPRERAPRJ936809). Its RERA-registered completion deadline (19 Jun 2021) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ936809 |
| Applicant type | Competent authority |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 20 Dec 2018 |
| Original start | 20 Dec 2018 |
| Project duration | 30 |
| Address | Moradabad, Moradabad |
| RERA registered | 15 Oct 2020 |
| Promised completion | 19 Jun 2021 |
| Revised completion | — none granted |
| Completion certificate filed | 11 May 2023 |
| Registration fee | ₹55,500 |
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 384 | 24 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 2882/AA.B.-1/PRABHARI NIDESHAK/2018-19 | 2 Jul 2018 | 2 Jul 2023 | 19 Jun 2021 |
| Khasra | Area | Type |
|---|---|---|
| 2407/1 | 10033 | Khasra |
Other projects registered in Moradabad.
Yes. Construction of 384 EWS Houses under PMAY (Urban) Scheme at Lakri Fazalpur Gata No. 2407/1, Moradabad is registered with UPRERA under registration number UPRERAPRJ936809, registered on 15 Oct 2020. Estanzo reproduces that filing; it does not verify the work behind it.
UPRERA still lists Construction of 384 EWS Houses under PMAY (Urban) Scheme at Lakri Fazalpur Gata No. 2407/1, Moradabad as Registered, so it is not shown as completed here. A completion certificate dated 11 May 2023 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Construction of 384 EWS Houses under PMAY (Urban) Scheme at Lakri Fazalpur Gata No. 2407/1, Moradabad is registered in Moradabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗