Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad

UPRERARegistered

Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is a RERA-registered residential project by Ghaziabad Development Authority in Ghaziabad (RERA ID UPRERAPRJ520694). Registered with a completion deadline of 9 Mar 2022. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ520694
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start11 Mar 2019
Project duration36 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompetent authority
Applicant addressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    263/FC/EEZONE-3/2019

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 Jul 2019
Original completion10 Sept 2021
Revised completion9 Mar 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹75,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors432 · 9 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK43223
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
BLOCK 1 · 1 BHK44823
BLOCK 2 · 1 BHK44823
BLOCK 3 · 1 BHK44823
BLOCK 4 · 1 BHK44823
BLOCK 5 · 1 BHK44823
BLOCK 6 · 1 BHK44823
BLOCK 7 · 1 BHK44823
BLOCK 8 · 1 BHK44823
BLOCK 9 · 1 BHK44823
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
PLANNING SECTION
License NA
GHAZIABAD DEVELOPMENT AUTHORITY GHAZIABAD
Engineer
JAMIA MILIA ISLAMIA UNIVERSITY
NEW DELHI
Contractor
SUNIL GARG AND COMPANY
150 EAST MODAL TOWN GHAZIABAD
Sr.Development work declared to RERA
1Demarcation of Plots
NORTH- ABADI, SOUTH-ROAD, EAST-ABADI, WEST-ROAD/ABADI
2Boundary Wall
5 FT HEIGHT BOUNDARY WALL SHOULD BE CONSTRUCTED
3Road Work
IN 6MTR WIDE ROAD 1 LAYER GSB THEN 80MM THICK RUBBER MOLDED INTERLOCKING TILES IN 5MTR WIDTH, IN MAINS ROADS 1 LAYER GSB, WMM, DBM. AND THEN BC ARE PROPOSED
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
WATER SUPPLY SHOULD BE PROVIDED O/H/T DISTRIBUTION LINE 110MM DIA HDPE PIPE
6Sewer System
THROUGH RCC HUME PIPE 300DIA AND 250MM DIA VIA STP
7Drain
BRICK IN DRAIN IN CEMENT MORTAR AND THEN PLASTER
8Parks
BRICK IN BOUNDARY WALL AND INNERSIDE GREEN PLANTATION
9Tree Planting
PROPOSED
10Design For Electric Supply Including Street Lighting
TO BE PROVIDED THROUGH SUBSTATION PROPOSED
11Community Buildings
TO BE PROPOSED
12Treatment and Disposal System of Sewage and Sullage water
TO BE PROVIDED BY STP
13Solid Waste Management And Disposal System
TO BE PROVIDED BY NAGAR NIGAM
14Water Conservation System
NA
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
FIRE HYDRANT SHOULD BE PROVIDED IN WATER MAIN
17Social Infrastructure And Other Public Amenities Including Public Health Services
SPACE PROVIDED FOR COMMUNITY FACILITIES
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 7 Mar 2024.

Sanctioned by Ghaziabad Development Authority · 14,074 sqm of land · an approved plan of 9 blocks and 432 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
263/FC/EEZONE-3/20198 Mar 20197 Mar 20246 Mar 202710 Sept 2021
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 9 Mar 2022.

#Granted fromExtended uptoNote
110 Sept 20219 Mar 2022Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
2301MI14620Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 5093/8-60/2016-18
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Jul 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New1 Jul 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New1 Jul 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New1 Jul 2019 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New14 Jun 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New1 Jul 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New1 Jul 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New1 Jul 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New1 Jul 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Jul 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New1 Jul 2019 ↗

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGhaziabad Development Authority
RolePromoter · current
RERA IDUPRERAPRM11404
PANAAALG0072C
CIN / TANMRTG00108D
Registered addressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
VC GDA PMAYBankVIJAYA BANKBranchNAVYUG MARKETA/C no.IFSCVIJB0007113
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad

Is Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad RERA registered?

Yes. Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is registered with UPRERA under registration number UPRERAPRJ520694, registered on 16 Jul 2019. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

The completion date filed with UPRERA is 9 Mar 2022. No completion certificate is on record yet.

Who is the builder of Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

Ghaziabad Development Authority is the promoter entity that filed Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad with UPRERA (promoter RERA ID UPRERAPRM11404). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad more time to complete?

UPRERA's record carries 1 completion extension for Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad, the latest running to 9 Mar 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad located?

Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

The approved unit plan describes 9 blocks and 432 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

About 124 units per acre: 432 planned units across 3.48 acres (14,074 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗