Timeline Bar

Registered16 Jul 2019
Promised10 Sept 2021
Today4 Aug 2026

Timeline

Promised completion10 Sept 2021
Revised completion10 Sept 2021
Actual completion
Possession delay59 mo delay

Registration & Cost Details

Registration fee (in ₹)₹75,500
Project cost (in ₹ Lakhs)₹3,388 Lakhs
Project duration36 months
Project categoryResidential
Locality
Original start date
Proposed start date11 Mar 2019

Inventory

Total units432
Unit TypeUnitsCarpet Area (sqm)
1 BHK43222.67

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9711630738
Emailgdagzb@rediffmail.com
Coordinator9643326705
AddressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
263/FC/EEZONE-3/20198 Mar 20197 Mar 202410 Sept 20216 Mar 2027

Land Parcels

Khasra No.AreaPlot Type
2301MI14620Khasra

Approved Unit Plan

Unit plan rows on file36
Total flats (sum of rows)432
BlocksBLOCK 1, BLOCK 2, BLOCK 3, BLOCK 4, BLOCK 5, BLOCK 6, BLOCK 7, BLOCK 8, BLOCK 9
Floor types1 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

The RERA registration number of Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is UPRERAPRJ520694, as recorded on the UP-RERA portal.

What is the RERA status of Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad?

As reported by UP-RERA, the status of Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is "Registered".

Where is Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad located?

As reported to UP-RERA, Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad be completed?

The latest completion date reported to UP-RERA for Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is 10 Sept 2021.

Is Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad delayed?

Measured against the latest completion date reported to UP-RERA, Construction of 432 EWS units under PMAY Scheme at Dasna Ghaziabad is 59 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.