Estanzo

Timeline Bar

Registered30 Jul 2017
Promised30 Sept 2017
Completed27 May 2019

Timeline

Promised completion30 Sept 2017
Revised completion30 Sept 2017
Actual completion27 May 2019
Possession delay20 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,53,000
Project cost (in ₹ Lakhs)₹32,500 Lakhs
Project duration76 months
Project categoryResidential
Locality
Original start date15 Jun 2011
Proposed start date15 Jun 2011

Inventory

Total units462
Unit TypeUnitsCarpet Area (sqm)
2 BHK26481.63–84.75
3 BHK198107.5–110.45

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9711630738
Emailgdagzb@rediffmail.com
Coordinator9415305084
AddressVikas Path, Near Purana Bus Adda, Hapur Road, Ghaziabad 201001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
memo/niyojan-anu/20111 Feb 201128 Jan 201630 Sept 201731 Mar 2018

Approved Unit Plan

Unit plan rows on file14
Total flats (sum of rows)462
BlocksCran Berry Type A, Cran Berry Type B, Golden Berry Type A, Golden Berry Type B, Golden Wood Type A, Golden Wood Type B, Holy Oak Type A, Holy Oak Type B, Mill Berry Type A, Mill Berry Type B, Rasp Berry Type A, Rasp Berry Type B, Ten Oak Type A, Ten Oak Type B
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Construction of 463 Multistoried Apartments on GH-?

The RERA registration number of Construction of 463 Multistoried Apartments on GH- is UPRERAPRJ5874, as recorded on the UP-RERA portal.

What is the RERA status of Construction of 463 Multistoried Apartments on GH-?

As reported by UP-RERA, the status of Construction of 463 Multistoried Apartments on GH- is "Registered".

Where is Construction of 463 Multistoried Apartments on GH- located?

As reported to UP-RERA, Construction of 463 Multistoried Apartments on GH- is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is Construction of 463 Multistoried Apartments on GH- completed?

As reported to UP-RERA, Construction of 463 Multistoried Apartments on GH- was completed on 27 May 2019.

Is Construction of 463 Multistoried Apartments on GH- delayed?

Measured against the latest completion date reported to UP-RERA, Construction of 463 Multistoried Apartments on GH- is 20 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026