Estanzo

Timeline Bar

Registered16 Apr 2018
Promised30 Sept 2019
Today4 Aug 2026

Timeline

Promised completion30 Sept 2019
Revised completion30 Sept 2019
Actual completion
Possession delay82 mo delay

Registration & Cost Details

Registration fee (in ₹)₹27,000
Project cost (in ₹ Lakhs)₹1,350 Lakhs
Project duration18 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2018

Inventory

Total units54
Unit TypeUnitsCarpet Area (sqm)
3 BHK36158
4 BHK18176

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9258024370
Emailm.sagar@fmglass.com
Coordinator9258024370
AddressFM INFRACITY FIROZABAD

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
92/201310 Dec 20149 Dec 201930 Sept 20199 Dec 2022
92/2013

Revalidated: 92/2013 (10 Dec 2014)

10 Dec 20149 Dec 2019

Revalidated upto: 1 Jan 1900

30 Sept 20199 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
5724400SQ MTR

Approved Unit Plan

Unit plan rows on file27
Total flats (sum of rows)54
BlocksLILY TOWER, TULIP TOWER
Floor types3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
6583 Feb 2012

Frequently Asked Questions

What is the RERA registration number of COSMOS?

The RERA registration number of COSMOS is UPRERAPRJ15744, as recorded on the UP-RERA portal.

What is the RERA status of COSMOS?

As reported by UP-RERA, the status of COSMOS is "Registered".

Where is COSMOS located?

As reported to UP-RERA, COSMOS is located at Firozabad, Firozabad, Uttar Pradesh.

When will COSMOS be completed?

The latest completion date reported to UP-RERA for COSMOS is 30 Sept 2019.

Is COSMOS delayed?

Measured against the latest completion date reported to UP-RERA, COSMOS is 82 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026