Timeline Bar
Registered9 Aug 2017
Promised31 Dec 2019
Today4 Aug 2026
Timeline
Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion—
Possession delay79 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,42,000
Project cost (in ₹ Lakhs)₹4,781 Lakhs
Project duration46 months
Project categoryCommercial
Locality—
Original start date1 Mar 2016
Proposed start date1 Mar 2016
Inventory
Total units222714
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| OTHER | 222714 | 4.852–886.498 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8586928776
Emailrera_2017@imperiastructures.in
Coordinator9643808635,01146469999
AddressA-25, Mohan Co-operative Industrial Estate Mathura Road, New Delhi-110044
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| PLG/(BP)-2254/2642 | 23 Mar 2011 | 22 Mar 2013 | 31 Dec 2019 | 31 Dec 2019 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 44/45 | 80953 | Plot |
Approved Unit Plan
Unit plan rows on file93
Total flats (sum of rows)222714
BlocksCYBER
Floor typesOTHER
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of Cyber?
The RERA registration number of Cyber is UPRERAPRJ5566, as recorded on the UP-RERA portal.
What is the RERA status of Cyber?
As reported by UP-RERA, the status of Cyber is "Registered".
Where is Cyber located?
As reported to UP-RERA, Cyber is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
When will Cyber be completed?
The latest completion date reported to UP-RERA for Cyber is 31 Dec 2019.
Is Cyber delayed?
Measured against the latest completion date reported to UP-RERA, Cyber is 79 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026