DESERVE ELITE is a RERA-registered residential project by DESERVE BUILDERS & DEVELOPER LIMITED in Lucknow (RERA ID UPRERAPRJ7004). Registered with a completion deadline of 17 Aug 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
36%Q3'25
36%Q4'25
40%Q1'26
43%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7004
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start18 Nov 2014
Original start11 Nov 2013
Project duration141 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant addressDeserve Group CST Road, Next to Kotak Mahindra Bank, Opp.University of Mumbai, Kalina , Santacruz (East) MUMBAI-400098
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Permit revalidated (2)

  3. 3 building permits sanctioned

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion30 Dec 2021
Revised completion17 Aug 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹65,000
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors236 · 7 · 16 (units from plan)
  • 3 BHK113 48%
  • 2 BHK93 39%
  • 4 BHK30 13%
ConfigurationUnitsCarpet area
4 BHK30155-161
3 BHK11376-130
2 BHK9373-81
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 4 BHK, OTHER1628155-161
B · 2 BHK, 3 BHK, OTHER165673-107
C · 3 BHK, 2 BHK, OTHER165673-107
D · 4 BHK, 3 BHK, OTHER44120-158
E · 2 BHK, OTHER51276-76
F · OTHER20—
G · 3 BHK, 2 BHK, OTHER168079-130
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
REPUNJAY PATEL
License CA/2001/28562
ARCHITECT AVENUE, D-2/122, GR. FLOOR, SAMBHAV TOWER, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW, U.P. - 226010
Engineer
MAHIMTURA CONSULTANTS PVT. LTD.
UNIQUE HOUSE, 3RD FLOOR, 25 S.A.BRELVI ROAD, MUMBAI - 400 001.
Contractor
DESERVE CONSTRUCTION PRIVATE LIMITED
DESERVE GROUP, CST ROAD, NEAR KOTAK BANK, OPP. MUMBAI UNIVERSITY PREMISES, KALINA, SANTACRUZ EAST, MUMBAI - 400098
Sr.Development work declared to RERA
1Demarcation of Plots
Plot no GH7/Sector 11, Vrindavan Yojna, Awas Vikas, Raebareilly Road, Lucknow admeasuring 11944 Sq.mtrs allotted by UPAEVP.
2Boundary Wall
Approximately 2100 mm high, along entire periphery.
3Road Work
Cement Concrete Road.
4Footpaths
Interlocking Pavers.
5Water Supply Including Drinking Water Facilities
One underground Tank of 200 KL capacity with pumping station & 1 Overhead tank in each of the 7 towers.
6Sewer System
Underground System.
7Drain
Semi covered Drain System in entire premises.
8Parks
Parks will be provided as approved
9Tree Planting
Approx. 60 Trees will be there
10Design For Electric Supply Including Street Lighting
Four Electricity Transformers each 750 KVA & 2 DG Sets for Power Back up for electric supply including street lighting.
11Community Buildings
Community hall & Club House provided
12Treatment and Disposal System of Sewage and Sullage water
Underground sewage treatment plant (STP) with recycle water system.
13Solid Waste Management And Disposal System
Manual Collection.
14Water Conservation System
Rainwater Harvesting facilities shall be provided & treated sewage water shall be recycles to the extent feasible.
15Energy Management System Including Use of Renewable Energy
Solar panels shall be provided on terrace for renewable energy. Single point metering will be there for energy purchased from the grid/power supply company.
16Fire Protection And Fire Safety System
Fire tender path shall be provided as per NBC. Fire fighting system along with pumps and water storage tanks shall be provided as per NBC & NOC from fire department. Also, Fire alarm system, Fire extinguishers & Sprinklers shalll be provided in Common & Basement area of the project.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Community Hall inside the Club for Residents, Swimmimg Pool, Parks, Jogging Track, Gymnasium, Indoor Game Center.
18Emergency Evacuation Services
Fire Doors & Fire Exit.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1RANVEER PROPERTIESUPRERAAGT10234
2RELIVE SOLUTIONS PVT. LTD.UPRERAAGT10078
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 17 Nov 2019. 2 of them carry a revalidation, the latest valid to 17 Nov 2022.

Sanctioned by U.P. Awas Evam Vikas Parishad · 11,944 sqm of land · an approved plan of 7 blocks and 236 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
2387/N.P./2014/7818 Nov 201417 Nov 201916 Nov 202230 Dec 2021—
2387/N.P./2014/7818 Nov 201417 Nov 201916 Nov 202230 Dec 202118 Nov 2014
2387/N.P./2014/7818 Nov 201417 Nov 201917 Aug 202629 Jun 202218 Nov 2014
valid to 17 Nov 2022
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 17 Aug 2026.

#Granted fromExtended uptoNote
130 Dec 202129 Jun 2022Six months extension in view of force majeure caused by covid-19 pandemic
229 Jun 202217 Aug 2026—

Land & documents

34 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
3693570 sq.mtrs—
3702530 sq. mtrs—
371 (mi)4110 sq. mtrs—
372580 sq. mtrs—
373290 sq. mtrs—
375864 sq. mtrs—
3693570Khasra
3702530Khasra
371(mi)4110Khasra
372580Khasra
373290Khasra
375864Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

3 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 6 Apr 2013.

Registry no.DateTypeArea
59586 Apr 2013other—
59586 Apr 2013other—
59586 Apr 2013other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 5958
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Registry document · 5958
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New5 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New5 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old19 Mar 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old19 Mar 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
Old19 Mar 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old19 Mar 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old19 Mar 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old19 Mar 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old19 Mar 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old19 Mar 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old19 Mar 2018 ↗

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q236%CA ↗ · Arch ↗ · Eng ↗
2025-Q336%CA ↗ · Arch ↗ · Eng ↗
2025-Q440%CA ↗ · Arch ↗ · Eng ↗
2026-Q143%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameDESERVE BUILDERS & DEVELOPER LIMITED
RolePromoter · current
RERA IDUPRERAPRM1930
PANAADCD4203G
CIN / TANU70102MH2010PLC201082
Name of chairmanSantosh Sarda
Registered addressDeserve Group CST Road, Next to Kotak Mahindra Bank, Opp.University of Mumbai, Kalina , Santacruz (East) MUMBAI-400098
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
DESERVE BUILDERS AND DEVELOPER LIMITEDBankUNION BANK OF INDIABranchSACHIVALAYA BRANCH LUCKNOWA/C no.IFSCUBIN0538159
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)5 (Under Registration - 0 )
first recorded by Estanzo
18 Oct 2026
Revised completion date on file2026-08-17
first recorded by Estanzo
18 Oct 2026
Completion date promised at registration2021-12-30
first recorded by Estanzo
18 Oct 2026
Promoter’s complaints tally (all their projects)5 (Under Registration - 0 )
no longer on the record
15 Oct 2026
Revised completion date on file2026-08-17
no longer on the record
15 Oct 2026
Completion date promised at registration2021-12-30
no longer on the record
15 Oct 2026
When these facts last moved
Revised completion date on filefirst recorded by Estanzo · 18 Oct 2026 · 2 movements on record
Promoter’s complaints tally (all their projects)first recorded by Estanzo · 18 Oct 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about DESERVE ELITE

Is DESERVE ELITE RERA registered?

Yes. DESERVE ELITE is registered with UPRERA under registration number UPRERAPRJ7004, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for DESERVE ELITE?

The completion date filed with UPRERA is 17 Aug 2026. No completion certificate is on record yet.

Who is the builder of DESERVE ELITE?

DESERVE BUILDERS & DEVELOPER LIMITED is the promoter entity that filed DESERVE ELITE with UPRERA (promoter RERA ID UPRERAPRM1930). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted DESERVE ELITE more time to complete?

UPRERA's record carries 2 completion extensions for DESERVE ELITE, the latest running to 17 Aug 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does DESERVE ELITE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is DESERVE ELITE located?

DESERVE ELITE is registered in Lucknow, as filed with UPRERA.

What configurations are available in DESERVE ELITE?

The unit plan filed with UPRERA lists 4 BHK, 3 BHK, 2 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in DESERVE ELITE?

The approved unit plan filed with UPRERA runs from 73 to 161 m² of carpet area (about 788 to 1,729 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in DESERVE ELITE?

The approved unit plan describes 7 blocks and 236 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is DESERVE ELITE?

About 80 units per acre: 236 planned units across 2.95 acres (11,944 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗