Timeline Bar

Registered31 Jul 2017
Promised27 Nov 2019
Revised25 May 2021
Completed2 Nov 2021

Timeline

Promised completion27 Nov 2019
Revised completion25 May 2021
Actual completion2 Nov 2021
Possession delay5 mo delay

Registration & Cost Details

Registration fee (in ₹)₹71,000
Project cost (in ₹ Lakhs)₹0 Lakhs
Project duration90 months
Project categoryResidential
Locality
Original start date28 Nov 2013
Proposed start date28 Nov 2013

Inventory

Total units292
Unit TypeUnitsCarpet Area (sqm)
1 BHK4825–35
3 BHK19495.34–98.65
4 BHK50130.61–135.91

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile8953331111
Emailtintingoel85@gmail.com
Coordinator8953331111
Address51/91, Nayaganj, Kanpur

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
277/ENF/16-174 Feb 20173 Feb 202227 Nov 20193 Feb 2023
277/ENF/16-17

Revalidated: 277/ENF/16-17 (4 Feb 2017)

4 Feb 20173 Feb 2022

Revalidated upto: 3 Feb 2023

27 Nov 20193 Feb 2023
277/ENF/16-17

Revalidated: 277/ENF/16-17 (4 Feb 2017)

4 Feb 20173 Feb 2022

Revalidated upto: 3 Feb 2025

25 May 20213 Feb 2025

Land Parcels

Khasra No.AreaPlot Type
13913112Plot

Approved Unit Plan

Unit plan rows on file171
Total flats (sum of rows)292
BlocksA, B, C, D, E, LIG/EWS
Floor types1 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
-9 Sept 2013

Frequently Asked Questions

What is the RERA registration number of Dilbagh Rose Garden?

The RERA registration number of Dilbagh Rose Garden is UPRERAPRJ6221, as recorded on the UP-RERA portal.

What is the RERA status of Dilbagh Rose Garden?

As reported by UP-RERA, the status of Dilbagh Rose Garden is "Registered".

Where is Dilbagh Rose Garden located?

As reported to UP-RERA, Dilbagh Rose Garden is located at Kanpur, Kanpur Nagar, Uttar Pradesh.

Is Dilbagh Rose Garden completed?

As reported to UP-RERA, Dilbagh Rose Garden was completed on 2 Nov 2021.

Is Dilbagh Rose Garden delayed?

Measured against the latest completion date reported to UP-RERA, Dilbagh Rose Garden is 5 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026