Estanzo

Timeline Bar

Registered26 Dec 2025
Today4 Aug 2026
Promised30 Nov 2029

Timeline

Promised completion30 Nov 2029
Revised completion30 Nov 2029
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹51,000
Project cost (in ₹ Lakhs)₹6,686 Lakhs
Project duration50 months
Project categoryCommercial
LocalityBakwal, Sadar, Maunath Bhanjan, Mau
Original start date
Proposed start date1 Oct 2025

Inventory

Total units52
Unit TypeUnitsCarpet Area (sqm)
SHOP3413.25–554.67
OTHER1857.41–588.06

Promoters & Contact

Contact Details

Applicant TypeProprietorship Firm
Mobile9198880005
Emaileasternmallmau@gmail.com
Coordinator8477094541
AddressFlat No.: B-2/81, Lal Pariksha Bhawan, Sector F, Near Chai Bolo Chai, Jankipuram, Lucknow, Uttar Pradesh, 226021

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2025-Q310.0%
2025-Q411.0%
2026-Q113.6%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
6722 Dec 202430 Nov 202930 Nov 202929 Nov 2032

Land Parcels

Khasra No.AreaPlot Type
30 MI4098Khasra

Approved Unit Plan

Unit plan rows on file55
Total flats (sum of rows)52
Total shops34
BlocksEastern Mall
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of EASTERN MALL?

The RERA registration number of EASTERN MALL is UPRERAPRJ802689, as recorded on the UP-RERA portal.

What is the RERA status of EASTERN MALL?

As reported by UP-RERA, the status of EASTERN MALL is "Registered".

Where is EASTERN MALL located?

As reported to UP-RERA, EASTERN MALL is located at Khasra No 30 MI, Mauza- Bakwal, Tehsil-Sadar, District- Mau, PIN- 276402, Bakwal, Sadar, Maunath Bhanjan, Mau, Maunath Bhanjan, Mau, Uttar Pradesh.

When will EASTERN MALL be completed?

The latest completion date reported to UP-RERA for EASTERN MALL is 30 Nov 2029.

Is EASTERN MALL delayed?

Measured against the latest completion date reported to UP-RERA, EASTERN MALL is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026