Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
10%Q4'25
11%Q1'26
13.56%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ802689
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAny Other Competent Authority
Proposed start1 Oct 2025
Project duration50 months
AddressKhasra No 30 MI, Mauza- Bakwal, Tehsil-Sadar, District- Mau, PIN- 276402, Bakwal, Sadar, Maunath Bhanjan, Mau, Maunath Bhanjan, Mau
TehsilMaunath Bhanjan
Applicant typeProprietorship Firm
Applicant addressFlat No.: B-2/81, Lal Pariksha Bhawan, Sector F, Near Chai Bolo Chai, Jankipuram, Lucknow, Uttar Pradesh, 226021
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    672

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered26 Dec 2025
Original completion30 Nov 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹51,000
Sanctioning authorityAny Other Competent Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors52 · 1 · 9 (units from plan)
Homes · commercial units18 · 34 (shops and offices filed in the same plan)
  • SHOP34 65%
  • OTHER18 35%
ConfigurationUnitsCarpet area
SHOP3413-49
OTHER1857-588
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Eastern Mall · SHOP, OTHER95213-588
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 300.9 m² for a SHOP, 554.67 m² for a SHOP, 554.67 m² for a SHOP, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Abhineet Srivastava
License CA/2012/54718
Tatsat Lane 5, Radha Baba Marg, Shankarpuri Sector-3, Shivpur Sahbazganj, Gorakhpur, UP
Engineer
Satyanam Sharan
1/353 I, Vinamra Khand, Gomti Nagar, Lucknow, UP
Contractor
AVAYAVA CONSTRUCTION CO. UP
D-3/172, Vikalp Khand, Gomti Nagar, Lucknow, 226010
Sr.Development work declared to RERA
1Demarcation of Plots
North- 93.87 mtr, South- 97.25 mtr, East- 41.72 mtr, West- 44.72 mtr with area under development for approval is 4097.73 sqmt.
2Boundary Wall
Approximately 250 mts long boundary with Elegant Design Integrated with security rails and patterns shall be provided.
3Road Work
Peripheral loop of road connect to each retail entry points with dedicated drop off plaza for cars to stop and drop the visitors.
4Footpaths
Not Applicable.
5Water Supply Including Drinking Water Facilities
Shall be provided through concerned local authorities keeping in view that supply facility shall be provided as per calculation based upon the NBC. The potable water will be delivered through overhead tanks.
6Sewer System
Centralized STP (75 KLD) to treat the sewage and building having its own down comer connected to the main sewerage line as per Approved Drawing. It will be connected through manholes laid along the building.
7Drain
Centralized STP (75 KLD) to treat the sewage and building having its own down comer connected to the main sewerage line As per Approved Drawing.
8Parks
Not Applicable.
9Tree Planting
Trees will be planted along the periphery of the project.
10Design For Electric Supply Including Street Lighting
Single Feeder shall be obtained from UPPCL and connect to the central substation and entire project shall have street lighting.
11Community Buildings
Not Applicable .
12Treatment and Disposal System of Sewage and Sullage water
Central STP for entire project and building shall be connected to STP.
13Solid Waste Management And Disposal System
Project shall have waste segregation area and OWC for treatment of Organic Waste .
14Water Conservation System
Adequate number of Recharge Pits shall be made with multilayered filter system to collect rainwater and allow percolation through perforated pipe to assist ground water recharge.
15Energy Management System Including Use of Renewable Energy
LED lights and solar light panels shall be used for efficient energy management.
16Fire Protection And Fire Safety System
Wet riser will be installed in the project with dedicated water storage tank. The hydrants will also be placed at the required norms as per building codes.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable.
18Emergency Evacuation Services
Exit signage in common areas shall be provided followed by evacuation plan to assist the occupants, emergency light and general awareness boards will be placed in the project.
19Other Miscellaneous Work
As per project requirement.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 30 Nov 2029.

Sanctioned by Any Other Competent Authority · 4,098 sqm of land · an approved plan of 1 block and 52 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
6722 Dec 202430 Nov 202929 Nov 203230 Nov 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
30 MI4098Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1427-1432 (01 July 2019 to 30 jUNE 2025)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · IN-UP59027038394248X
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New15 Dec 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New4 Nov 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New4 Nov 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New4 Nov 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Dec 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New4 Nov 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New4 Nov 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Nov 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Nov 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Nov 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New4 Nov 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New4 Nov 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New6 Nov 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New4 Nov 2025 ↗

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q1.

QuarterConstructionCertificates
2025-Q310%CA ↗ · Arch ↗ · Eng ↗
2025-Q411%CA ↗ · Arch ↗ · Eng ↗
2026-Q113.56%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameEastern Mall
RolePromoter · current
RERA IDUPRERAPRM397845
PANANSPS4572L
CIN / TANLKNR15558E
Registered addressFlat No.: B-2/81, Lal Pariksha Bhawan, Sector F, Near Chai Bolo Chai, Jankipuram, Lucknow, Uttar Pradesh, 226021
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
M/s. Eastern Mall R Coll A/c For Eastern MallBankHDFC Bank Ltd.BranchMau Nath BhanjanBranch addressHDFC Bank Ltd. Jyoti Tower, Sahadatpura, Mau Nath Bhanjan, Uttar Pradesh, 275102Branch districtMau, Uttar PradeshA/C no.IFSCHDFC0001910Branch emailsantosh.tiwari1@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
M/s. Eastern Mall R Sep A/c For Eastern MallBankHDFC Bank Ltd.BranchMau Nath BhanjanBranch addressHDFC Bank Ltd. Jyoti Tower, Sahadatpura, Mau Nath Bhanjan, Uttar Pradesh, 275102Branch districtMau, Uttar PradeshA/C no.IFSCHDFC0001910
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
M/s. Eastern Mall R Tran A/c For Eastern MallBankHDFC Bank Ltd.BranchMau Nath BhanjanBranch addressHDFC Bank Ltd. Jyoti Tower, Sahadatpura, Mau Nath Bhanjan, Uttar Pradesh, 275102Branch districtMau, Uttar PradeshA/C no.IFSCHDFC0001910
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about EASTERN MALL

Is EASTERN MALL RERA registered?

Yes. EASTERN MALL is registered with UPRERA under registration number UPRERAPRJ802689, registered on 26 Dec 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for EASTERN MALL?

The completion date filed with UPRERA is 30 Nov 2029. No completion certificate is on record yet.

Who is the builder of EASTERN MALL?

Eastern Mall is the promoter entity that filed EASTERN MALL with UPRERA (promoter RERA ID UPRERAPRM397845). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does EASTERN MALL have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is EASTERN MALL located?

EASTERN MALL is registered in Bakwal, Sadar, Maunath Bhanjan, Mau, Mau, as filed with UPRERA.

What configurations are available in EASTERN MALL?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in EASTERN MALL?

The approved unit plan filed with UPRERA runs from 13 to 588 m² of carpet area (about 143 to 6,330 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in EASTERN MALL?

The approved unit plan describes 1 block and 52 units of which 18 are homes and 34 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is EASTERN MALL?

About 51 units per acre: 52 planned units across 1.01 acres (4,098 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗