Registered15 Apr 2025
Today4 Aug 2026
Promised9 Dec 2029

Timeline

Promised completion9 Dec 2029
Revised completion9 Dec 2029
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹16,500
Project cost (in ₹ Lakhs)₹343 Lakhs
Project duration60 months
Project categoryResidential
LocalityBarbara Majra
Original start date
Proposed start date10 Dec 2024

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeIndividual
Mobile9927780777
EmailKuldeepsun@gmail.com
Coordinator8881133311
AddressGali No -2, Khushal Nagar, Moradabad, UP, Pin Code244001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q3
2024-Q4
2025-Q1
2025-Q228.1%
2025-Q328.0%
2025-Q428.0%
2026-Q128.1%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
683/Mu.Vi.Pra/R.B.O./2024-2510 Dec 20249 Dec 20299 Dec 20299 Dec 2032

Land Parcels

Khasra No.AreaPlot Type
177, 178, 1792326.86Khasra

Frequently Asked Questions

What is the RERA registration number of Ekkta Enclave?

The RERA registration number of Ekkta Enclave is UPRERAPRJ110595, as recorded on the UP-RERA portal.

What is the RERA status of Ekkta Enclave?

As reported by UP-RERA, the status of Ekkta Enclave is "Registered".

Where is Ekkta Enclave located?

As reported to UP-RERA, Ekkta Enclave is located at Khasra No -177 Mi , 178 Mi , & 179 Mi Barbara Majhra, Ekta Vihar South, Nera Water Tank, Moradabad, Barbara Majra, Moradabad, Moradabad, Uttar Pradesh.

When will Ekkta Enclave be completed?

The latest completion date reported to UP-RERA for Ekkta Enclave is 9 Dec 2029.

Is Ekkta Enclave delayed?

Measured against the latest completion date reported to UP-RERA, Ekkta Enclave is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026