Timeline Bar
Registered15 Apr 2025
Today4 Aug 2026
Promised9 Dec 2029
Timeline
Promised completion9 Dec 2029
Revised completion9 Dec 2029
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹16,500
Project cost (in ₹ Lakhs)₹343 Lakhs
Project duration60 months
Project categoryResidential
LocalityBarbara Majra
Original start date—
Proposed start date10 Dec 2024
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile9927780777
EmailKuldeepsun@gmail.com
Coordinator8881133311
AddressGali No -2, Khushal Nagar, Moradabad, UP, Pin Code244001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 683/Mu.Vi.Pra/R.B.O./2024-25 | 10 Dec 2024 | 9 Dec 2029 | 9 Dec 2029 | 9 Dec 2032 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 177, 178, 179 | 2326.86 | Khasra |
Frequently Asked Questions
What is the RERA registration number of Ekkta Enclave?
The RERA registration number of Ekkta Enclave is UPRERAPRJ110595, as recorded on the UP-RERA portal.
What is the RERA status of Ekkta Enclave?
As reported by UP-RERA, the status of Ekkta Enclave is "Registered".
Where is Ekkta Enclave located?
As reported to UP-RERA, Ekkta Enclave is located at Khasra No -177 Mi , 178 Mi , & 179 Mi Barbara Majhra, Ekta Vihar South, Nera Water Tank, Moradabad, Barbara Majra, Moradabad, Moradabad, Uttar Pradesh.
When will Ekkta Enclave be completed?
The latest completion date reported to UP-RERA for Ekkta Enclave is 9 Dec 2029.
Is Ekkta Enclave delayed?
Measured against the latest completion date reported to UP-RERA, Ekkta Enclave is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026