EYE OF NOIDA (EON) BLOCK-E

UPRERARegistered

EYE OF NOIDA (EON) BLOCK-E is a RERA-registered commercial project by FAIRFOX ITINFRA PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ716606). Registered with a completion deadline of 31 Jan 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
50.85%Q3'25
50.85%Q4'25
59.26%Q1'26
62.68%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ716606
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Mar 2022
Project duration59 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressPLOT NO.01A, SECTOR-140A, NOIDA-201305
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2021/12/17/5968

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 Mar 2022
Original completion31 Jan 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,49,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors819 · 1 · 16 (units from plan)
Homes · commercial units681 · 138 (shops and offices filed in the same plan)
  • OTHER681 83%
  • SHOP138 17%
ConfigurationUnitsCarpet area
SHOP13810-151
OTHER6814-88
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
E · SHOP, OTHER168194-151
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 489.39 m² for a SHOP, 380.57 m² for a SHOP, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANAND SHARMA
License CA/95/18738
K-47,KAILASH COLONY, NEW DELHI-110048
Engineer
DR. MAQSUDE NAZAR
G-70, 2ND FLOOR, JASWANT PLAZA, NEAR KALINDI KUNJ, SARITA VIHAR, NEW DLEHI-110025
Contractor
FAIRFOX ITINFRA PRIVATE LIMITED
PLOT NO.01A, SECTOR-140A, NOIDA-201305
Sr.Development work declared to RERA
1Demarcation of Plots
The Project land will be demarcated by its boundry wall to the exact shape and size as per the site plan sanctioned by Noida Authority
2Boundary Wall
2400mm High boundry wall of combination of RCC column/beam with brickwork/ ms work
3Road Work
Road work is proposed with Trimix concreate flooring with P.C.C. base
4Footpaths
Footpaths is proposed with combination of kerb stone/pavers on compacted subgrade which will be lasting and visible at all conditions.
5Water Supply Including Drinking Water Facilities
the main source of drinking water will be ground water and shall be extracted through tube well and supplied by under ground and overhead water tank.
6Sewer System
The soil and waste shall be carried down in separate independently vented pipes . two pipe drainage system shall be adopted as per ASPE standard
7Drain
separate and independent rainwater drainage system shall be provided for collecting rainwater from terrace , paved area, lawns and roads
8Parks
the provision of parks in our project will be as per the sanction plan approved by the noida authority
9Tree Planting
Proposed native adaptive Planting scheme in such a way that the planting design respond to the physiological needs of the place
10Design For Electric Supply Including Street Lighting
33 kv incoming supply shall be provided which shall be converted in 415v supply and same shall be feed to the entire system. The time switch operated street lights shall be provide the lux level shall be meet as per NBC-2016 guidelines.
11Community Buildings
the provision of community buildings is not applicable as per sanctioned plan approved by noida authority
12Treatment and Disposal System of Sewage and Sullage water
The provision of sewage treatment plant for treatment of sewage and sullage waste. The plant shall comprise of preliminary and secondary (chemical and biological) and tertiary treatment plant.
13Solid Waste Management And Disposal System
The provision of solid waste management and disposal system will as per norms applicable
14Water Conservation System
low water flow fixtures are used to conserve the water for the project.
15Energy Management System Including Use of Renewable Energy
Less or Non-movement area sensor shall be provided . Hybridge solar system shall be provided as renewable energy, it will be synchronising with main supply
16Fire Protection And Fire Safety System
As per fire norms provided in NBC-2016 with the fire tender, sprinkler system, smoke detector etc.
17Social Infrastructure And Other Public Amenities Including Public Health Services
The social infrastructure and other Public Amenities including PHS will be provided as per the norms provide by the authority.
18Emergency Evacuation Services
Sufficient wide range of staircase as desired with signage planned as per NBC-2016
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
2WEST WAY REALTY SERVICES PRIVATE LIMITEDUPRERAAGT21913
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 3 Feb 2027.

Sanctioned by Noida Authority · 13,812 sqm of land · an approved plan of 1 block and 819 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2021/12/17/59684 Feb 20223 Feb 20273 Feb 202831 Jan 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
01A13812Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 2866
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Feb 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Feb 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Feb 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Feb 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New14 Mar 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New25 Feb 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New25 Feb 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 Feb 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Feb 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New25 Feb 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Feb 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Feb 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New14 Mar 2022 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q4 to 2026-Q2.

QuarterConstructionCertificates
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q250.85%CA ↗ · Arch ↗ · Eng ↗
2025-Q350.85%CA ↗ · Arch ↗ · Eng ↗
2025-Q459.26%CA ↗ · Arch ↗ · Eng ↗
2026-Q162.68%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameFAIRFOX ITINFRA PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM149539
PANAAECF5428J
CIN / TANMRTF01671F
Name of chairmanNEERAJ JINDAL
Registered addressPLOT NO.01A, SECTOR-140A, NOIDA-201305
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
FAIRFOX ITINFRA PRIVATE LIMITED COLLECTION A/C FOR EYE OF NOIDA BLOCK-EBankAXIS BANK LTDBranchINDIRAPURAMBranch addressINDIRAPURAM, GHAZIABAD-201010Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0000636
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
FAIRFOX ITINFRA PVT LTD SEPARATE BANK A/C FOR EYE OF NOIDA BLOCK-EBankAXIS BANK LTDBranchINDIRAPURAMBranch addressINDIRAPURAM , GHAZIABAD-201010Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0000636
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
FAIRFOX ITINFRA PRIVATE LIMITED FOR EYE OF NOIDA BLOCK-EBankAXIS BANK LTDBranchINDIRAPURAMBranch addressINDIRAPURAM, GHAZIABAD-201010Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0000636
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

5 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)8 (Under Registration - 1 ) → 8 (Under Registration - 0 )
changed in Estanzo’s record
18 Oct 2026
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
13 Oct 2026
Promoter’s complaints tally (all their projects)7 (Under Registration - 0 ) → 8 (Under Registration - 1 )
changed in Estanzo’s record
5 Oct 2026
Promoter’s complaints tally (all their projects)7 (Under Registration - 2 ) → 7 (Under Registration - 0 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)5 (Under Registration - 0 ) → 7 (Under Registration - 2 )
changed in Estanzo’s record
31 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 4 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about EYE OF NOIDA (EON) BLOCK-E

Is EYE OF NOIDA (EON) BLOCK-E RERA registered?

Yes. EYE OF NOIDA (EON) BLOCK-E is registered with UPRERA under registration number UPRERAPRJ716606, registered on 16 Mar 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for EYE OF NOIDA (EON) BLOCK-E?

The completion date filed with UPRERA is 31 Jan 2027. No completion certificate is on record yet.

Who is the builder of EYE OF NOIDA (EON) BLOCK-E?

FAIRFOX ITINFRA PRIVATE LIMITED is the promoter entity that filed EYE OF NOIDA (EON) BLOCK-E with UPRERA (promoter RERA ID UPRERAPRM149539). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does EYE OF NOIDA (EON) BLOCK-E have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is EYE OF NOIDA (EON) BLOCK-E located?

EYE OF NOIDA (EON) BLOCK-E is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in EYE OF NOIDA (EON) BLOCK-E?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in EYE OF NOIDA (EON) BLOCK-E?

The approved unit plan filed with UPRERA runs from 4 to 151 m² of carpet area (about 38 to 1,624 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in EYE OF NOIDA (EON) BLOCK-E?

The approved unit plan describes 1 block and 819 units of which 681 are homes and 138 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is EYE OF NOIDA (EON) BLOCK-E?

About 240 units per acre: 819 planned units across 3.41 acres (13,812 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗