Timeline Bar

Registered21 Feb 2018
Promised28 Feb 2022
Revised27 Aug 2022
Today4 Aug 2026

Timeline

Promised completion28 Feb 2022
Revised completion27 Aug 2022
Actual completion
Possession delay47 mo delay

Registration & Cost Details

Registration fee (in ₹)₹45,000
Project cost (in ₹ Lakhs)₹4,200 Lakhs
Project duration118 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Mar 2018

Inventory

Total units375
Unit TypeUnitsCarpet Area (sqm)
SHOP357–25.13
OTHER34016.1–37.74

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9811943402
Emailhcd.rera@gmail.com
Coordinator9718580746
AddressA-19, Sector-64, Noida, Uttar Pradesh-201301

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q10.0%
2020-Q20.0%
2020-Q30.0%
2020-Q40.0%
2021-Q10.0%
2021-Q20.0%
2021-Q30.0%
2021-Q40.0%
2022-Q11.7%
2022-Q28.2%
2022-Q316.4%
2022-Q428.7%
2023-Q134.7%
2023-Q238.5%
2023-Q341.9%
2023-Q442.0%
2024-Q142.7%
2024-Q243.1%
2024-Q344.1%
2024-Q446.7%
2025-Q146.7%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP3625/1103

Revalidated: PLG/BP-SM-04-DEC-2024;23257 (11 Apr 2025)

15 Feb 201814 Feb 2023

Revalidated upto: 13 Feb 2028

27 Aug 202212 Feb 2031
BP3625/1103

Revalidated: BP3625/1103 (15 Feb 2018)

15 Feb 201814 Feb 2023

Revalidated upto: 14 Feb 2028

27 Aug 202213 Feb 2031
BP3625/1103

Revalidated: PLG/BP-SM-04-DEC-2024;23257 (11 Apr 2025)

15 Feb 201814 Feb 2023

Revalidated upto: 13 Feb 2028

27 Aug 202213 Feb 2028

Approved Unit Plan

Unit plan rows on file73
Total flats (sum of rows)375
Total shops35
BlocksBLOCK-3 AND 12
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
199638 Sept 2015

Frequently Asked Questions

What is the RERA registration number of Galactic City-Universal Tower?

The RERA registration number of Galactic City-Universal Tower is UPRERAPRJ15254, as recorded on the UP-RERA portal.

What is the RERA status of Galactic City-Universal Tower?

As reported by UP-RERA, the status of Galactic City-Universal Tower is "Registered".

Where is Galactic City-Universal Tower located?

As reported to UP-RERA, Galactic City-Universal Tower is located at N/A, Gautam Budh Nagar, Uttar Pradesh.

When will Galactic City-Universal Tower be completed?

The latest completion date reported to UP-RERA for Galactic City-Universal Tower is 27 Aug 2022.

Is Galactic City-Universal Tower delayed?

Measured against the latest completion date reported to UP-RERA, Galactic City-Universal Tower is 47 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026