Registered10 Aug 2017
Promised31 Dec 2018
Today4 Aug 2026

Timeline

Promised completion31 Dec 2018
Revised completion31 Dec 2018
Actual completion
Possession delay91 mo delay

Registration & Cost Details

Registration fee (in ₹)₹36,500
Project cost (in ₹ Lakhs)₹6,000 Lakhs
Project duration54 months
Project categoryResidential
Locality
Original start date8 Jul 2014
Proposed start date8 Jul 2014

Inventory

Total units225
Unit TypeUnitsCarpet Area (sqm)
2 BHK10064.4
3 BHK12569.54–82.06

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9953558659
EmailDdrsanjeev1@gmail.com
Coordinator9999899772
AddressH-95,Sector-63, Noida-201 301

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP2425/44/GH57318 Jul 20147 Jul 201931 Dec 20187 Jul 2024
BP2425/44/GH57318 Jul 20147 Jul 201931 Dec 20187 Jul 2024

Land Parcels

Khasra No.AreaPlot Type
Plot No: GC-03, Gaur City, GH-01, Sector-4Greater Noida (West), Gautam Budh Nagar, U.P.
GC-03 / GAUR CITY, GH-01, SECTOR-4, GREATER NOIDA,20000Plot

Approved Unit Plan

Unit plan rows on file75
Total flats (sum of rows)225
BlocksG
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
2053726 Aug 2010

Frequently Asked Questions

What is the RERA registration number of Galaxy North Avenue (Tower G)?

The RERA registration number of Galaxy North Avenue (Tower G) is UPRERAPRJ5458, as recorded on the UP-RERA portal.

What is the RERA status of Galaxy North Avenue (Tower G)?

As reported by UP-RERA, the status of Galaxy North Avenue (Tower G) is "Registered".

Where is Galaxy North Avenue (Tower G) located?

As reported to UP-RERA, Galaxy North Avenue (Tower G) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Galaxy North Avenue (Tower G) be completed?

The latest completion date reported to UP-RERA for Galaxy North Avenue (Tower G) is 31 Dec 2018.

Is Galaxy North Avenue (Tower G) delayed?

Measured against the latest completion date reported to UP-RERA, Galaxy North Avenue (Tower G) is 91 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026