Ganpati Infinity BLOCK-G/DIVINE HOMEZ

UPRERAAbeyance

Ganpati Infinity BLOCK-G/DIVINE HOMEZ is a RERA-registered residential project by GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED in Mathura (RERA ID UPRERAPRJ7667). RERA status: Abeyance.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Abeyance.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Oct–Dec 2020
Quarters shown are calendar quarters. UP-RERA files them by financial year.
93%Q2'20
93%Q3'20
93%Q4'20

Construction stayed at 93% across 3 consecutive filed quarters (Apr–Jun 2020 to Oct–Dec 2020). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7667
Project categoryResidential
Registration typeOngoing
RERA statusAbeyanceAbeyance“Held in suspension.” UP-RERA lists projects whose registration it has placed in abeyance.Read the full entry in the glossary
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMathura-Vrindavan Development Authority
Proposed start1 Aug 2017
Original start18 Nov 2015
Project duration39 months
AddressMathura, Mathura
TehsilMathura
Applicant typeCompany
Applicant address31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    21/V-09-10

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Abeyance. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Aug 2017
Original completion12 Apr 2020
Revised completion11 Oct 2020
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹34,000
Sanctioning authorityMathura-Vrindavan Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors96 · 8 · 3 (units from plan)
ConfigurationUnitsCarpet area
2 BHK9655
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
43 · 2 BHK31255
44 · 2 BHK31255
45 · 2 BHK31255
46 · 2 BHK31255
47 · 2 BHK31255
48 · 2 BHK31255
49 · 2 BHK31255
50 · 2 BHK31255
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
YESHVIR SINGH
License CA/2000/25908
KHANDARI, AGRA
Engineer
DR. SANTOSH KUMAR
KANPUR
Contractor
PETTY CONTRACTORS /MUSTROLL LABOUR
AGRA
Sr.Development work declared to RERA
1Demarcation of Plots
YES
2Boundary Wall
YES
3Road Work
YES
4Footpaths
NO
5Water Supply Including Drinking Water Facilities
YES
6Sewer System
YES
7Drain
YES
8Parks
YES
9Tree Planting
YES
10Design For Electric Supply Including Street Lighting
YES
11Community Buildings
YES
12Treatment and Disposal System of Sewage and Sullage water
YES
13Solid Waste Management And Disposal System
YES
14Water Conservation System
YES
15Energy Management System Including Use of Renewable Energy
no
16Fire Protection And Fire Safety System
YES
17Social Infrastructure And Other Public Amenities Including Public Health Services
no
18Emergency Evacuation Services
no
19Other Miscellaneous Work
YES
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 11 Apr 2017.

Sanctioned by Mathura-Vrindavan Development Authority · 5,705 sqm of land · an approved plan of 8 blocks and 96 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
21/V-09-1012 Apr 201211 Apr 201712 Apr 202012 Apr 2020
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 11 Oct 2020.

#Granted fromExtended uptoNote
112 Apr 202011 Oct 2020Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

1 filing

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
205, 206, 20723850 SQ MTR—
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 9 Feb 2012.

Registry no.DateTypeArea
21679 Feb 2012self—

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterYES
Fire safety (as filed with RERA)YES
Other facilitiesPARK, KIDS PARK, RCC ROADS, FOUNTAIN. BASEMENT PARKING, SWIMMING POOL

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2020-Q3.

QuarterConstructionCertificates
2020-Q193%CA ↗ · Arch ↗ · Eng ↗
2020-Q293%CA ↗ · Arch ↗ · Eng ↗
2020-Q393%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2020-Q3. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED
RolePromoter · current
RERA IDUPRERAPRM2735
PANAAECG6731F
CIN / TANU70102UP2012PLC049767
Name of chairmanANIL AGARWAL
Registered address31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Mathura

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
GPL BUILDTECH PVT LTDBankHDFC BANK LTDBranchSANJAY PLACEA/C no.IFSCHDFC0000121
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)24 (Under Registration - 1 ) → 24 (Under Registration - 0 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 23 Aug 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Ganpati Infinity BLOCK-G/DIVINE HOMEZ

Is Ganpati Infinity BLOCK-G/DIVINE HOMEZ RERA registered?

Yes. Ganpati Infinity BLOCK-G/DIVINE HOMEZ is registered with UPRERA under registration number UPRERAPRJ7667, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Ganpati Infinity BLOCK-G/DIVINE HOMEZ?

The completion date filed with UPRERA is 11 Oct 2020. No completion certificate is on record yet.

Who is the builder of Ganpati Infinity BLOCK-G/DIVINE HOMEZ?

GANPATI INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED is the promoter entity that filed Ganpati Infinity BLOCK-G/DIVINE HOMEZ with UPRERA (promoter RERA ID UPRERAPRM2735). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Ganpati Infinity BLOCK-G/DIVINE HOMEZ more time to complete?

UPRERA's record carries 1 completion extension for Ganpati Infinity BLOCK-G/DIVINE HOMEZ, the latest running to 11 Oct 2020. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Ganpati Infinity BLOCK-G/DIVINE HOMEZ have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Ganpati Infinity BLOCK-G/DIVINE HOMEZ located?

Ganpati Infinity BLOCK-G/DIVINE HOMEZ is registered in Mathura, as filed with UPRERA.

What configurations are available in Ganpati Infinity BLOCK-G/DIVINE HOMEZ?

The unit plan filed with UPRERA lists 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Ganpati Infinity BLOCK-G/DIVINE HOMEZ?

The approved unit plan describes 8 blocks and 96 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Ganpati Infinity BLOCK-G/DIVINE HOMEZ?

About 68 units per acre: 96 planned units across 1.41 acres (5,705 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗