Registered14 Aug 2017
Promised31 Jul 2020
Today4 Aug 2026

Timeline

Promised completion31 Jul 2020
Revised completion31 Jul 2020
Actual completion
Possession delay72 mo delay

Registration & Cost Details

Registration fee (in ₹)₹59,500
Project cost (in ₹ Lakhs)₹16,200 Lakhs
Project duration107 months
Project categoryResidential
Locality
Original start date12 Oct 2011
Proposed start date5 Mar 2012

Inventory

Total units300
Unit TypeUnitsCarpet Area (sqm)
2 BHK8067.285–134.874
3 BHK20599.585–199.98
4 BHK15140.825

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310234153
Emailbhardwaj@gardeniaindia.com
Coordinator8800947771
AddressG-6/376, Block-G, Pocket-6,Rohini, Sector16, Delhi

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Noida/III 223/46012 Oct 201111 Oct 201631 Jul 202011 Oct 2021

Land Parcels

Khasra No.AreaPlot Type
NIL0
0910800Plot

Approved Unit Plan

Unit plan rows on file223
Total flats (sum of rows)300
BlocksD, E, F
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1/280117 Jun 2010

Frequently Asked Questions

What is the RERA registration number of Gardenia Gateway (Phase-I)?

The RERA registration number of Gardenia Gateway (Phase-I) is UPRERAPRJ11023, as recorded on the UP-RERA portal.

What is the RERA status of Gardenia Gateway (Phase-I)?

As reported by UP-RERA, the status of Gardenia Gateway (Phase-I) is "Registered".

Where is Gardenia Gateway (Phase-I) located?

As reported to UP-RERA, Gardenia Gateway (Phase-I) is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will Gardenia Gateway (Phase-I) be completed?

The latest completion date reported to UP-RERA for Gardenia Gateway (Phase-I) is 31 Jul 2020.

Is Gardenia Gateway (Phase-I) delayed?

Measured against the latest completion date reported to UP-RERA, Gardenia Gateway (Phase-I) is 72 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026