Registered31 Jul 2017
Revised2 May 2022
Promised31 Oct 2022
Today4 Aug 2026

Timeline

Promised completion31 Oct 2022
Revised completion2 May 2022
Actual completion
Possession delay51 mo delay

Registration & Cost Details

Registration fee (in ₹)₹28,36,000
Project cost (in ₹ Lakhs)₹40,500 Lakhs
Project duration109 months
Project categoryResidential
Locality
Original start date1 Nov 2013
Proposed start date1 Nov 2013

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582279254
Emailgaurshitech@gaursonsindia.com
Coordinator01204343333
AddressGaur Biz Park Plot No-1, Abhay Khand-II Indirapuram, Ghaziabad, U.P. Pin-201014

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG(BP)/3065/22534 May 20173 May 20222 May 20222 May 2027

Land Parcels

Khasra No.AreaPlot Type
Plot no. FH-03, SECTOR Agricultural Greens561727.95Plot

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
213283 Nov 2012

Frequently Asked Questions

What is the RERA registration number of Gaur Mulberry Mansions - FH-03?

The RERA registration number of Gaur Mulberry Mansions - FH-03 is UPRERAPRJ4897, as recorded on the UP-RERA portal.

What is the RERA status of Gaur Mulberry Mansions - FH-03?

As reported by UP-RERA, the status of Gaur Mulberry Mansions - FH-03 is "Registered".

Where is Gaur Mulberry Mansions - FH-03 located?

As reported to UP-RERA, Gaur Mulberry Mansions - FH-03 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Gaur Mulberry Mansions - FH-03 be completed?

The latest completion date reported to UP-RERA for Gaur Mulberry Mansions - FH-03 is 2 May 2022.

Is Gaur Mulberry Mansions - FH-03 delayed?

Measured against the latest completion date reported to UP-RERA, Gaur Mulberry Mansions - FH-03 is 51 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026