Registered28 Jul 2017
Promised31 Mar 2022
Today4 Aug 2026

Timeline

Promised completion31 Mar 2022
Revised completion31 Mar 2022
Actual completion
Possession delay52 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,05,000
Project cost (in ₹ Lakhs)₹62,162 Lakhs
Project duration117 months
Project categoryResidential
Locality
Original start date12 Jan 2013
Proposed start date12 Jan 2013

Inventory

Total units866
Unit TypeUnitsCarpet Area (sqm)
3 BHK76485.1–121.69
4 BHK51238.48–322.02
PENTHOUSE4192.13–272.61
SHOP4711.05–26.63

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582279254
Emailgaurssportswood@gaursonsindia.com
Coordinator01204343333
AddressB-159, Block-B, Yojna Vihar, Delhi-110095

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Noida/MVN/2016/IV-1394/91021 Jun 201620 Jun 202131 Mar 202219 Jun 2026

Land Parcels

Khasra No.AreaPlot Type
SC-01/E140000Plot

Approved Unit Plan

Unit plan rows on file293
Total flats (sum of rows)866
Total shops47
BlocksBLOCK-A, BLOCK-B, BLOCK-C, BLOCK-D, BLOCK-E, BLOCK-F, BLOCK-G, BLOCK-H, BLOCK-I, BLOCK-J, BLOCK-K, GAUR SPORTSWOOD- ARCADE
Floor types3 BHK, 4 BHK, PENTHOUSE, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Gaur Sportswood?

The RERA registration number of Gaur Sportswood is UPRERAPRJ3528, as recorded on the UP-RERA portal.

What is the RERA status of Gaur Sportswood?

As reported by UP-RERA, the status of Gaur Sportswood is "Registered".

Where is Gaur Sportswood located?

As reported to UP-RERA, Gaur Sportswood is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Gaur Sportswood be completed?

The latest completion date reported to UP-RERA for Gaur Sportswood is 31 Mar 2022.

Is Gaur Sportswood delayed?

Measured against the latest completion date reported to UP-RERA, Gaur Sportswood is 52 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026