Timeline Bar

Registered31 Jul 2017
Promised19 Jan 2024
Today4 Aug 2026

Timeline

Promised completion19 Jan 2024
Revised completion19 Jan 2024
Actual completion
Possession delay30 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,85,000
Project cost (in ₹ Lakhs)₹31,300 Lakhs
Project duration121 months
Project categoryResidential
Locality
Original start date22 Jan 2014
Proposed start date10 Jul 2014

Inventory

Total units1728
Unit TypeUnitsCarpet Area (sqm)
2 BHK54451.82–57.89
3 BHK95662.88–148.66
SHOP477–77.72
STUDIO18122.47–49.54

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8130488558
EmailHARIOMDIXIT@HOTMAIL.COM
Coordinator8130488558
AddressGH11, SECTOR 1, GREATER NOIDA(WEST), GAUTAM BUDH NAGAR, UTTAR PRADESH

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP-2681/GH/ORA-5370

Revalidated: PLG/(BP)2681/1145 (16 Feb 2018)

28 Aug 201327 Aug 2018

Revalidated upto: 19 Jan 2024

19 Jan 202419 Jan 2024

Land Parcels

Khasra No.AreaPlot Type
GH11, SECTOR 1, GREATER NOIDA WEST36002.95Plot

Approved Unit Plan

Unit plan rows on file1753
Total flats (sum of rows)1728
Total shops47
BlocksA, B, C, D, E, F, G, H, I, J, Studio Tower
Floor types2 BHK, 3 BHK, SHOP, STUDIO, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of GAYATRI AURA?

The RERA registration number of GAYATRI AURA is UPRERAPRJ7084, as recorded on the UP-RERA portal.

What is the RERA status of GAYATRI AURA?

As reported by UP-RERA, the status of GAYATRI AURA is "Registered".

Where is GAYATRI AURA located?

As reported to UP-RERA, GAYATRI AURA is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will GAYATRI AURA be completed?

The latest completion date reported to UP-RERA for GAYATRI AURA is 19 Jan 2024.

Is GAYATRI AURA delayed?

Measured against the latest completion date reported to UP-RERA, GAYATRI AURA is 30 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026