Registered13 Aug 2017
Revised14 Dec 2022
Promised16 Dec 2022
Today4 Aug 2026

Timeline

Promised completion16 Dec 2022
Revised completion14 Dec 2022
Actual completion
Possession delay44 mo delay

Registration & Cost Details

Registration fee (in ₹)₹45,000
Project cost (in ₹ Lakhs)₹200 Lakhs
Project duration102 months
Project categoryResidential
Locality
Original start date18 Jun 2007
Proposed start date16 Dec 2014

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9761865070
Emailgghousing001@gmail.com
Coordinator9808865069
Address36/1680, NAI WALA KAROL BAGH NEW DELHI

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1708/BFL/3/05-06

Revalidated: 1708/BFL/3/05-06 (16 Dec 2017)

18 Jun 200717 Jun 2012

Revalidated upto: 15 Dec 2022

14 Dec 202214 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
54,55,5613557

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1/5033/381-414/836816 Nov 2006
4933-1/36/64407 Aug 2006
1/5703/79-100/359613 Jun 2008

Frequently Asked Questions

What is the RERA registration number of GG VILLAGE?

The RERA registration number of GG VILLAGE is UPRERAPRJ10366, as recorded on the UP-RERA portal.

What is the RERA status of GG VILLAGE?

As reported by UP-RERA, the status of GG VILLAGE is "Registered".

Where is GG VILLAGE located?

As reported to UP-RERA, GG VILLAGE is located at Agra, Agra, Uttar Pradesh.

When will GG VILLAGE be completed?

The latest completion date reported to UP-RERA for GG VILLAGE is 14 Dec 2022.

Is GG VILLAGE delayed?

Measured against the latest completion date reported to UP-RERA, GG VILLAGE is 44 months beyond that date.