Timeline Bar

Registered15 Aug 2017
Promised5 Mar 2020
Completed1 Aug 2020

Timeline

Promised completion5 Mar 2020
Revised completion5 Mar 2020
Actual completion1 Aug 2020
Possession delay5 mo delay

Registration & Cost Details

Registration fee (in ₹)₹42,000
Project cost (in ₹ Lakhs)₹12,842 Lakhs
Project duration97 months
Project categoryResidential
Locality
Original start date4 Mar 2011
Proposed start date5 Mar 2012

Inventory

Total units264
Unit TypeUnitsCarpet Area (sqm)
2 BHK10255.83–85.83
3 BHK16231.94–99.5

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9311146329
Emailfinance@golfcity.in
Coordinator+919310234138
AddressR-19, 3rd FLOOR, NEAR SHAKARPUR, LAXMI NAGAR, VIKAS MARG DELHI East Delhi DL 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2021-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/III-243/3524 Mar 20114 Mar 20165 Mar 20204 Mar 2021
NOIDA/CAP/III-243/3524 Mar 20113 Mar 20165 Mar 20204 Mar 2021

Land Parcels

Khasra No.AreaPlot Type
NIL0
GH-1123916Plot

Approved Unit Plan

Unit plan rows on file147
Total flats (sum of rows)264
BlocksF2, G2, H2
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
91531 Jan 2011

Frequently Asked Questions

What is the RERA registration number of GH-11/75 (PHASE-3) GOLF CITY?

The RERA registration number of GH-11/75 (PHASE-3) GOLF CITY is UPRERAPRJ11557, as recorded on the UP-RERA portal.

What is the RERA status of GH-11/75 (PHASE-3) GOLF CITY?

As reported by UP-RERA, the status of GH-11/75 (PHASE-3) GOLF CITY is "Registered".

Where is GH-11/75 (PHASE-3) GOLF CITY located?

As reported to UP-RERA, GH-11/75 (PHASE-3) GOLF CITY is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is GH-11/75 (PHASE-3) GOLF CITY completed?

As reported to UP-RERA, GH-11/75 (PHASE-3) GOLF CITY was completed on 1 Aug 2020.

Is GH-11/75 (PHASE-3) GOLF CITY delayed?

Measured against the latest completion date reported to UP-RERA, GH-11/75 (PHASE-3) GOLF CITY is 5 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.