Godrej Jardinia

UPRERARegistered

Godrej Jardinia is a RERA-registered mixed project by Godrej Properties Limited in Sector-146, NOIDA, Gautam Budh Nagar (RERA ID UPRERAPRJ288309). Registered with a completion deadline of 3 Dec 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
10.84%Q3'25
12.28%Q4'25
20%Q1'26
21.05%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ288309
Project categoryMixed
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Apr 2024
Project duration57 months
AddressPlot No. GH-01B, Sector-146, NOIDA, Sector-146, NOIDA, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressGodrej One, 5th Floor, Pirojshanagar, Eastern Express Highway, Vikhroli (East), Mumbai – 400079
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2023/08/18/9428

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered8 Apr 2024
Original completion3 Dec 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,95,750
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors720 · 6 · 36 (units from plan)
Homes · commercial units700 · 20 (shops and offices filed in the same plan)
  • OTHER350 49%
  • 3 BHK320 44%
  • 2 BHK30 4%
  • SHOP20 3%
ConfigurationUnitsCarpet area
OTHER350127-159
3 BHK32091
2 BHK3077
SHOP2011-45
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Bellavue (Tower-1) · OTHER, 3 BHK, 2 BHK3614077-159
Commercial · SHOP12011-45
Courtyard (Tower-4) · OTHER, 3 BHK, 2 BHK3614077-127
Emperio (Tower-3) · OTHER, 3 BHK, 2 BHK3614077-159
Serein (Tower-2) · OTHER, 3 BHK, 2 BHK3614077-159
Verdure (Tower-5) · OTHER, 3 BHK, 2 BHK3614077-159
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Avanish Srivastav
License CA/2016/77184
Golden India Architects, FF-37, Kadamba Complex, Gamma-1, Greater Noida, Uttar Pradesh.
Engineer
Ms. Madhura Manjrekar
Dr. Kelkar Designs Pvt. Ltd. 610, Keshava, Bandra Kurla Complex, Bandra ( East), Mumbai - 450051
Contractor
Ms S. R. Infrastructure
G-361-A, Sector-11, Pratap Vihar, Ghaziabad, Uttar Pradesh - 201001
Sr.Development work declared to RERA
1Demarcation of Plots
Not Applicable
2Boundary Wall
elegant design integrated with security rails and patterns as per approved building plan.
3Road Work
Peripheral loop of road connects to each tower with a dedicated Drop off plaza for cars to access the respective towers as per approved building plan.
4Footpaths
Network of footpaths connects the various parts in the landscape, Towers and Gardens as per approved building plans.
5Water Supply Including Drinking Water Facilities
Noida Authority shall provide water supply to the society and it shall be stored in underground tanks which shall be pumped to overhead water tanks and further supplied at customer premises through gravity.
6Sewer System
Centralized STP to treat the sewerage and every tower has its own downcomers connected to main sewerage line which terminates in STP.
7Drain
Rainwater drainage system shall be provided for collecting rainwater from terrace, paved area, lawns and roads. Rainwater down takes of appropriate size and number shall be provided. The final disposal shall be in external municipal drain, no rainwater harvesting pit planned at site as the water table is high (only 5-6m below NGL). Rain Water Collection Tank is being planned accordingly.
8Parks
Green area to be provided as per approved plan. The project will have a landscape area with thematic gardens and decorative plants.
9Tree Planting
The trees will be planted at all suitable locations of the project and along the boundary walls. The tree selection, flora and vegetation shall be as per the IGBC requirements.
10Design For Electric Supply Including Street Lighting
Electrical supply shall be taken from UPPCL and connected to central substation and entire project shall have street lighting.
11Community Buildings
Community Building as per approved building plan.
12Treatment and Disposal System of Sewage and Sullage water
Central STP for entire project and all towers shall be connected to STP. Treated water shall be used for flushing and garden irrigation purposes.
13Solid Waste Management And Disposal System
Project shall have waste segregation and Organic waste convertor for treatment of organic waste.
14Water Conservation System
Low flow fixtures, dual plumbing system, dual flush cisterns shall be provided.
15Energy Management System Including Use of Renewable Energy
LED lights and timer control panels shall be used for efficient energy management, Solar PV cells shall be provided for renewable energy.
16Fire Protection And Fire Safety System
Fire Hydrant, sprinkler and fire alarm system shall be provided. the entire fire safety installation shall be compliant with the applicable codes/ standards for the complex to ensure the safety standard and uniformity of system.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Common social infrastructure shall be provided as per approved building plan.
18Emergency Evacuation Services
Exit signage in common areas shall be provided
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

28 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 DEGREE VENTURES PRIVATE LIMITEDUPRERAAGT18728
2ABHISHEK PANDEYUPRERAAGT16755
3Adarsh Kumar AgarwalUPRERAAGT17429
4AJAY BHADOURIYAUPRERAAGT15100
5AKHILESH SHARMAUPRERAAGT16700
6AMAN KHURANAUPRERAAGT18798
7ANAROCK Property Consultants Private LimitedUPRERAAGT10265
8Bajaj Capital Investment Centre LimitedUPRERAAGT11036
9BELPATRAM INFRATECH PRIVATE LIMITEDUPRERAAGT17551
10BLUECRUMBS INFRA PRIVATE LIMITEDUPRERAAGT16897
11BOP REALTY PRIVATE LIMITEDUPRERAAGT10206
12BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
13BUNIYAD REALTY LIMITED (Formerly BUNIYAD RETAIL INDIA PRIVATE LIMITED)UPRERAAGT11569
14CAPITALBOON CONSULTINGUPRERAAGT18663
15Cushman & Wakefield India Private LimitedUPRERAAGT11043
16EVERONN VALUE VENTURESUPRERAAGT13810
17FINDMYPROPERTY PRIVATE LIMITEDUPRERAAGT11867
18HAPPY HOMES REALTORS AND BUILDERSUPRERAAGT15217
19MADHYAM ESTATE LINKERS PVT LTDUPRERAAGT10509
20PROPSHOPUPRERAAGT10129
21Smart InfraReality Private LimitedUPRERAAGT10057
22star estateUPRERAAGT10202
23STEPYARD INFRATECH PRIVATE LIMITEDUPRERAAGT16057
24Supertrust Homes Pvt LtdUPRERAAGT16429
25Trisol RED Infraventures Pvt LtdUPRERAAGT11579
26VALUEMAX ADVISORS CONSULTING PRIVATE LIMITEDUPRERAAGT11361
27WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
28Yash BhardwajUPRERAAGT15511
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 3 Dec 2028.

Sanctioned by Noida Authority · 25,001 sqm of land · an approved plan of 6 blocks and 720 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2023/08/18/94284 Dec 20233 Dec 20282 Dec 20333 Dec 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH 01B Sector 146 Noida25001Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 1473
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Noida/GH/2022/15414
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New23 Dec 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 Dec 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New27 Dec 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Mar 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New23 Dec 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New23 Dec 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New23 Dec 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New23 Dec 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Mar 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New28 Jan 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 Jan 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Jan 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New6 Mar 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New6 Mar 2024 ↗

Quarterly progress reports

9 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

9 quarterly progress reports are on file with UPRERA, covering 2024-Q1 to 2026-Q1.

QuarterConstructionCertificates
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q210.84%CA ↗ · Arch ↗ · Eng ↗
2025-Q312.28%CA ↗ · Arch ↗ · Eng ↗
2025-Q420%CA ↗ · Arch ↗ · Eng ↗
2026-Q121.05%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGodrej Properties Limited
RolePromoter · current
RERA IDUPRERAPRM237988
PANAAACG3995M
CIN / TANMUMG08095D
Name of chairmanPirojsha Adi Godrej
Registered addressGodrej One, 5th Floor, Pirojshanagar, Eastern Express Highway, Vikhroli (East), Mumbai – 400079
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Godrej Properties Limited Collection A/c for Godrej JardiniaBankAxis BankBranchSector-12, NOIDABranch addressGround Floor, Shop No. 11, 12 and 13, Block I-25, Sector-12, NOIDA, Uttar Pradesh-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0002462Branch emailcustomer.service@axisbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Godrej Properties Limited Separate A/c for Godrej JardiniaBankAxis BankBranchSector-12, NOIDABranch addressGround Floor, Shop No. 11, 12 and 13, Block I-25, Sector-12, NOIDA, Uttar Pradesh-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0002462
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Godrej Properties Limited RERA Transaction A/c for Godrej JardiniaBankAxis BankBranchSector-12, NOIDABranch addressGround Floor, Shop No. 11, 12 and 13, BlockI-25, Sector-12, NOIDA, Uttar Pradesh-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCUTIB0002462
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Godrej Jardinia

Is Godrej Jardinia RERA registered?

Yes. Godrej Jardinia is registered with UPRERA under registration number UPRERAPRJ288309, registered on 8 Apr 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Godrej Jardinia?

The completion date filed with UPRERA is 3 Dec 2028. No completion certificate is on record yet.

Who is the builder of Godrej Jardinia?

Godrej Properties Limited is the promoter entity that filed Godrej Jardinia with UPRERA (promoter RERA ID UPRERAPRM237988). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Godrej Jardinia have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Godrej Jardinia located?

Godrej Jardinia is registered in Sector-146, NOIDA, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Godrej Jardinia?

The unit plan filed with UPRERA lists OTHER, 3 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Godrej Jardinia?

The approved unit plan filed with UPRERA runs from 11 to 159 m² of carpet area (about 119 to 1,714 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Godrej Jardinia?

The approved unit plan describes 6 blocks and 720 units of which 700 are homes and 20 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Godrej Jardinia?

About 117 units per acre: 720 planned units across 6.18 acres (25,001 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗