GOLDEN AVENUE-IIUPRERADelayed 49 mo
Home › Projects › Meerut › GOLDEN AVENUE-II

GOLDEN AVENUE-II

UPRERADelayed 49 moRegisteredupdated 4 Aug 2026

GOLDEN AVENUE-II is a RERA-registered real-estate project in Meerut (RERA ID UPRERAPRJ9843). Its RERA-registered completion deadline (30 Jun 2022) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
49 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹5
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
12 Aug 2017

Basic details

RERA IDUPRERAPRJ9843
Applicant typeCompany
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start1 Apr 2017
Original start1 Apr 2017
Project duration69
AddressMawana, Meerut

Registration & timeline

RERA registered12 Aug 2017
Promised completion30 Jun 2022
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹31,000

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
20/15-164 Jul 20153 Jul 202030 Jun 2022

Land & documents

4 filings
KhasraAreaType
974830.65—
9739168.66—
974830.65Khasra
9739168.66Khasra
Registry & lease deeds
Registry no.DateTypeArea
1641616 Dec 2013——
1642616 Dec 2013——

Quarterly progress reports

11 filed reports
QuarterConstructionCertificatesSource
2020-Q1—CA · Arch · Engview ↗
2020-Q2—CA · Arch · Engview ↗
2020-Q3—CA · Arch · Engview ↗
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only.

Nearby projects

Meerut

Other projects registered in Meerut.

"Ornate"
UPRERA ▲ 76 mo
131/144 Type Duplex and 69/142 Type Residential Houses in Sector-3, Scheme No. 11, Jagriti Vihar (Ext.), Meerut
UPRERA ▲ 15 mo
528 FLATS IN AIRPORT ENCLAVE, SECTOR-10, SHATABDI NAGAR, MEERUT
UPRERA ▲ 67 mo
A2Z COLONY
UPRERA no delay on record
Aashiyana Green Wood
UPRERA ▲ 16 mo
Abdullah Residency and Shoping Plaza
UPRERA no delay on record

Common questions about GOLDEN AVENUE-II

Is GOLDEN AVENUE-II RERA registered?

Yes. GOLDEN AVENUE-II is registered with UPRERA under registration number UPRERAPRJ9843, registered on 12 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Is GOLDEN AVENUE-II delayed?

GOLDEN AVENUE-II is 49 months past the completion date filed with UPRERA (30 Jun 2022), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is GOLDEN AVENUE-II located?

GOLDEN AVENUE-II is registered in Meerut, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 49 mo
QPR filingNo default reported
DistrictMeerut
Last updated4 Aug 2026

Location

AddressMeerut
View on map ↗

RERA buyer helpline

Coordinator8859320001
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=/84fU5ZiFAE=&hfFlag=34fLDxYRDAg=&NPJ6RAme=7hzePLC/y740gbhAitMSW3FfJIOpMZRY&PaURJEMAN4=ZL9MNERkNdaKAwazodsfpg==&IRSAHEB=D6PY3lyims8=)