Estanzo

Timeline Bar

Registered14 Oct 2021
Promised31 Dec 2024
Today29 Jul 2026

Timeline

Promised completion31 Dec 2024
Revised completion31 Dec 2024
Actual completion
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹3,91,500
Project cost (in ₹ Lakhs)₹63,161 Lakhs
Project duration48 months
Project categoryMixed
Locality
Original start date
Proposed start date1 Jan 2022

Inventory

Total units1850
Unit TypeUnitsCarpet Area (sqm)
SHOP136632.51–1669
OTHER1714352–1796

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9415041804
Emailskg1964@rediffmail.com
Coordinator9650072125
AddressWZ-1598, GL-46, GROUND FLOOR, NANGAL RAYA, NEW DELHI, WEST DELHI - 110046

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q234.2%
2025-Q353.9%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BPSM-28-MAR-2019/50655 Oct 20214 Oct 202631 Dec 20243 Oct 2027

Land Parcels

Khasra No.AreaPlot Type
19100095.25Plot

Approved Unit Plan

Unit plan rows on file65
Total flats (sum of rows)1850
Total shops136
BlocksG, H, I, IT 1, IT 2, J, RESIDENTIAL BLOCK
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Golden Grande "Phase-1"?

The RERA registration number of Golden Grande "Phase-1" is UPRERAPRJ301910, as recorded on the UP-RERA portal.

What is the RERA status of Golden Grande "Phase-1"?

As reported by UP-RERA, the status of Golden Grande "Phase-1" is "Registered".

Where is Golden Grande "Phase-1" located?

As reported to UP-RERA, Golden Grande "Phase-1" is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will Golden Grande "Phase-1" be completed?

The latest completion date reported to UP-RERA for Golden Grande "Phase-1" is 31 Dec 2024.

Is Golden Grande "Phase-1" delayed?

Measured against the latest completion date reported to UP-RERA, Golden Grande "Phase-1" is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026