GOMTI ESTATE PHASE-II is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ10256). Its RERA-registered completion deadline (31 Dec 2018) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ10256 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Jan 2014 |
| Original start | 1 Jan 2014 |
| Project duration | 60 |
| Address | N/A, Lucknow |
| RERA registered | 14 Aug 2017 |
| Promised completion | 31 Dec 2018 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹3,29,000 |
| Khasra | Area | Type |
|---|---|---|
| 458 | 0.0430 | — |
| 461 | 0.0648 | — |
| 462 | 0.0648 | — |
| 471 | 0.0360 | — |
| 472 | 0.0360 | — |
| 476 | 0.1610 | — |
| 480 | 0.0173 | — |
| 493 | 0.0974 | — |
| 496 | 0.0395 | — |
| 497 | 0.0299 | — |
| 500 | 0.2530 | — |
| 501 | 0.0207 | — |
| 503 | 0.0830 | — |
| 503 | 0.0830 | — |
| 516 | 0.1163 | — |
| 517 | 0.1020 | — |
| 525 | 0.0924 | — |
| 525 | 0.0924 | — |
| 526 | 0.1423 | — |
| 526 | 0.0237 | — |
| 526 | 0.0237 | — |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 5542 | 7 Apr 2016 | — | — |
Yes. GOMTI ESTATE PHASE-II is registered with UPRERA under registration number UPRERAPRJ10256, registered on 14 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
GOMTI ESTATE PHASE-II is 91 months past the completion date filed with UPRERA (31 Dec 2018), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
GOMTI ESTATE PHASE-II is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗