Data as reported by UP-RERA. Estanzo reproduces public filings as-is with source links and does not verify, rate or endorse any builder or project.
GOVIND COMPLEXUPRERADelayed 74 mo
Home › Projects › Gorakhpur › GOVIND COMPLEX

GOVIND COMPLEX

UPRERADelayed 74 moRegisteredupdated 4 Aug 2026

GOVIND COMPLEX is a RERA-registered real-estate project in Gorakhpur (RERA ID UPRERAPRJ10892). Its RERA-registered completion deadline (3 Jun 2020) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
74 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹10
Land area
not reported
Units (from plan)
24
Density (derived)
not reported
Towers
not reported
Config
5 BHK/SHOP
Carpet
526–675
Registered
14 Aug 2017

Basic details

RERA IDUPRERAPRJ10892
Applicant typePartnership Firm
Project categoryCommercial
Project typeother
RERA statusRegistered
Proposed start3 Jun 2017
Original start3 Jun 2017
Project duration42
AddressGorakhpur, Gorakhpur

Registration & timeline

RERA registered14 Aug 2017
Promised completion3 Jun 2020
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹24,000

Inventory

derived from unit plan
Total units · towers · floors24 · 1 · 4 (units from plan)
24units
  • SHOP22 92%
  • 5 BHK2 8%
ConfigurationUnitsCarpet area
SHOP22526–535
5 BHK2675
Towers as filedGOVIND COMPLEX
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
334/2015 , 335/20153 Jun 20173 Jun 20223 Jun 2020

Land & documents

3 filings
KhasraAreaType
3011531.59 M2—
30146.468 M2—
3011531.59Khasra
Registry & lease deeds
Registry no.DateTypeArea
144123 Feb 2015——
976619 Nov 2014——

Nearby projects

Gorakhpur

Other projects registered in Gorakhpur.

A D MALL
UPRERA ▲ 91 mo
AMBESHWARI BUILD CON
UPRERA ▲ 62 mo
ARBIT THE 25
UPRERA ▲ 7 mo
ASHTA SIDDHI TRADE CENTER
UPRERA ▲ 67 mo
Central Towers
UPRERA no delay on record
CHAUDHARY S S H MALL
UPRERA no delay on record

Common questions about GOVIND COMPLEX

Is GOVIND COMPLEX RERA registered?

Yes. GOVIND COMPLEX is registered with UPRERA under registration number UPRERAPRJ10892, registered on 14 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Is GOVIND COMPLEX delayed?

GOVIND COMPLEX is 74 months past the completion date filed with UPRERA (3 Jun 2020), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is GOVIND COMPLEX located?

GOVIND COMPLEX is registered in Gorakhpur, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 74 mo
QPR filingNo default reported
DistrictGorakhpur
Last updated4 Aug 2026

Location

AddressGorakhpur
View on map ↗

RERA buyer helpline

Coordinator7080909174
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=4LQJ98Tmpr8=&hfFlag=Vve7Vt7phxw2J45GP78XiQ==&NPJ6RAme=MEaFgf+AoJBHVJMh47GVIg==&PaURJEMAN4=ZL9MNERkNdZuPJMlXIX+cg==&IRSAHEB=D6PY3lyims8=)