Timeline Bar
Registered4 Aug 2017
Promised23 Mar 2019
Completed6 Aug 2020
Timeline
Promised completion23 Mar 2019
Revised completion23 Mar 2019
Actual completion6 Aug 2020
Possession delay16 mo delay
Registration & Cost Details
Registration fee (in ₹)₹2,09,000
Project cost (in ₹ Lakhs)₹574 Lakhs
Project duration96 months
Project categoryResidential
Locality—
Original start date24 Mar 2011
Proposed start date24 Mar 2011
Inventory
Total units410
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 96 | 32–35 |
| 2 BHK | 192 | 36–43 |
| VILLA | 122 | 50 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9837088122
Emailpradeepgriham@gmail.com
Coordinator9837088122
AddressA-96, Saraswati Lok, Delhi Road, Meerut
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 20/10 | 24 Mar 2011 | 23 Mar 2016 | 23 Mar 2019 | 23 Mar 2019 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 402-409,441-444,446,500,503,507-510,514 & 515 | 40723 | — |
| 405, 406, 443, 445, 509, 510, 511, 408, 441, 442, | 4761 | Khasra |
| 405,406,443,445,509,510,511,408,441,442,503,504,50 | 4761 | Khasra |
| 405,406,443,445,509,510,511 | 7105 | Khasra |
| 405,406,443,445,509,510,511 | 7105 | Khasra |
| 405,406,443,445,509,510,511,408,441,442,503,504,50 | 4761 | Khasra |
| 405,406,443,445,509,510,511 | 3553 | Khasra |
| 405,406,443,445,509,510,511,408,441,442,503,504,50 | 2380 | Khasra |
| 405,406,443,445,509,510,511,408,441,442,503,504,50 | 2380 | Khasra |
| 405,406,443,445,509,510,511 | 3552 | Khasra |
| 514 | 410 | Khasra |
| 409 | 3058 | Khasra |
| 507/2,515 | 4180 | Khasra |
Approved Unit Plan
Unit plan rows on file73
Total flats (sum of rows)410
BlocksA, B, C, D, E, F, G, H, I, J, K, L, S, T, V, Villa, W, X, Y
Floor types1 BHK, 2 BHK, VILLA
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 2936 | 17 Mar 2011 | — | — |
| 11411 | 19 Nov 2010 | — | — |
| 7469 | 4 Aug 2010 | — | — |
| 11413 | 19 Nov 2010 | — | — |
| 11722 | 1 Dec 2010 | — | — |
| 798 | 22 Jan 2011 | — | — |
| 11583 | 25 Nov 2010 | — | — |
| 11584 | 25 Nov 2010 | — | — |
| 11947 | 7 Dec 2010 | — | — |
| 2320 | 18 Mar 2010 | — | — |
| 380 | 17 Jan 2009 | — | — |
| 9455 | 30 Dec 2008 | — | — |
Frequently Asked Questions
What is the RERA registration number of Griham?
The RERA registration number of Griham is UPRERAPRJ6466, as recorded on the UP-RERA portal.
What is the RERA status of Griham?
As reported by UP-RERA, the status of Griham is "Registered".
Where is Griham located?
As reported to UP-RERA, Griham is located at Meerut, Meerut, Uttar Pradesh.
Is Griham completed?
As reported to UP-RERA, Griham was completed on 6 Aug 2020.
Is Griham delayed?
Measured against the latest completion date reported to UP-RERA, Griham is 16 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.