Registered14 Aug 2017
Promised15 Jun 2018
Today4 Aug 2026

Timeline

Promised completion15 Jun 2018
Revised completion15 Jun 2018
Actual completion
Possession delay98 mo delay

Registration & Cost Details

Registration fee (in ₹)₹10,940
Project cost (in ₹ Lakhs)₹270 Lakhs
Project duration22 months
Project categoryCommercial
Locality
Original start date15 Jun 2016
Proposed start date15 Sept 2016

Inventory

Total units123
Unit TypeUnitsCarpet Area (sqm)
SHOP11813.99–144.7
OTHER5166.4–166.6

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8176004150
Emailgsrbuilders46@gmail.com
Coordinator9793493333
Address273 5TH Floor new janpath complex hazratganj lucknow

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
165315 Jun 201614 Jun 202115 Jun 201814 Jun 2021
1653

Revalidated: 1653 (15 Jun 2016)

15 Jun 201614 Jun 2021

Revalidated upto: 1 Jan 1900

15 Jun 201814 Jun 2021
165315 Jun 201614 Jun 202115 Jun 201814 Jun 2021

Land Parcels

Khasra No.AreaPlot Type
6A/com3546.70
6A/com3546.70Plot

Approved Unit Plan

Unit plan rows on file13
Total flats (sum of rows)123
Total shops118
Blocks1, 2, 3, 4, 5, 9, 13
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
26039 Feb 2016

Frequently Asked Questions

What is the RERA registration number of GSR CENTRE POINT?

The RERA registration number of GSR CENTRE POINT is UPRERAPRJ10536, as recorded on the UP-RERA portal.

What is the RERA status of GSR CENTRE POINT?

As reported by UP-RERA, the status of GSR CENTRE POINT is "Registered".

Where is GSR CENTRE POINT located?

As reported to UP-RERA, GSR CENTRE POINT is located at Lucknow, Lucknow, Uttar Pradesh.

When will GSR CENTRE POINT be completed?

The latest completion date reported to UP-RERA for GSR CENTRE POINT is 15 Jun 2018.

Is GSR CENTRE POINT delayed?

Measured against the latest completion date reported to UP-RERA, GSR CENTRE POINT is 98 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026