Registration & Cost Details
Inventory
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 118 | 13.99–144.7 |
| OTHER | 5 | 166.4–166.6 |
Promoters & Contact
Contact Details
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1653 | 15 Jun 2016 | 14 Jun 2021 | 15 Jun 2018 | 14 Jun 2021 |
| 1653 Revalidated: 1653 (15 Jun 2016) | 15 Jun 2016 | 14 Jun 2021 Revalidated upto: 1 Jan 1900 | 15 Jun 2018 | 14 Jun 2021 |
| 1653 | 15 Jun 2016 | 14 Jun 2021 | 15 Jun 2018 | 14 Jun 2021 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 6A/com3 | 546.70 | — |
| 6A/com3 | 546.70 | Plot |
Approved Unit Plan
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 2603 | 9 Feb 2016 | — | — |
Frequently Asked Questions
What is the RERA registration number of GSR CENTRE POINT?
The RERA registration number of GSR CENTRE POINT is UPRERAPRJ10536, as recorded on the UP-RERA portal.
What is the RERA status of GSR CENTRE POINT?
As reported by UP-RERA, the status of GSR CENTRE POINT is "Registered".
Where is GSR CENTRE POINT located?
As reported to UP-RERA, GSR CENTRE POINT is located at Lucknow, Lucknow, Uttar Pradesh.
When will GSR CENTRE POINT be completed?
The latest completion date reported to UP-RERA for GSR CENTRE POINT is 15 Jun 2018.
Is GSR CENTRE POINT delayed?
Measured against the latest completion date reported to UP-RERA, GSR CENTRE POINT is 98 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026