Timeline Bar

Promised28 Dec 2016
Registered10 Aug 2017
Completed15 Apr 2019

Timeline

Promised completion28 Dec 2016
Revised completion28 Dec 2016
Actual completion15 Apr 2019
Possession delay28 mo delay

Registration & Cost Details

Registration fee (in ₹)₹63,000
Project cost (in ₹ Lakhs)₹17,500 Lakhs
Project duration39 months
Project categoryResidential
Locality
Original start date5 Oct 2013
Proposed start date5 Oct 2013

Inventory

Total units477
Unit TypeUnitsCarpet Area (sqm)
2 BHK655.651–77.382
3 BHK47173.184–103.63

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582255195
Emailimtiyaz.khan@gulshangroup.com
Coordinator9582255139
Address121, HARGOVIND ENCLAVE, DELHI 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/III-274/54523 Aug 201222 Aug 201728 Dec 201622 Aug 2022

Land Parcels

Khasra No.AreaPlot Type
GH03A,Sector-143,Noida50166.30Plot

Approved Unit Plan

Unit plan rows on file419
Total flats (sum of rows)477
BlocksL, M, N, O, P, Q
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
5397 BOOK NO.1 VOL NO.2578 PAGE NO.39 TO 747 Jul 2011

Frequently Asked Questions

What is the RERA registration number of GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q?

The RERA registration number of GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q is UPRERAPRJ8806, as recorded on the UP-RERA portal.

What is the RERA status of GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q?

As reported by UP-RERA, the status of GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q is "Registered".

Where is GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q located?

As reported to UP-RERA, GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q completed?

As reported to UP-RERA, GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q was completed on 15 Apr 2019.

Is GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q delayed?

Measured against the latest completion date reported to UP-RERA, GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q is 28 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026