Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ9493
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBareily Development Authority
Proposed start29 Sept 2014
Original start29 Sept 2014
Project duration84 months
AddressBareilly, Bareilly
TehsilBareilly
Applicant typeCompany
Applicant addressNavjeevan Apartments, Opp. Parag Factory, Kargaina, Budaun Road, bareilly (U.P.)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    202/02

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. to

    Extension granted

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered11 Aug 2017
Original completion28 Sept 2019
Revised completion25 Sept 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹81,500
Sanctioning authorityBareily Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors412 · 3 · 4 (units from plan)
  • 2 BHK348 84%
  • 3 BHK64 16%
ConfigurationUnitsCarpet area
3 BHK6459-63
2 BHK34840-43
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CLUSTER A · 3 BHK46459-63
CLUSTER B · 2 BHK416041
CLUSTER C · 2 BHK418840-43
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUPAM SAXENA
License NA
BAREILLY
Engineer
NA
NA
Contractor
FAHIM KHAN
BAREILLY
Sr.Development work declared to RERA
1Demarcation of Plots
N.A
2Boundary Wall
2.10 MT HT. , 115 MM THICK BRICK WORK BOUNDARY WALL INCLUDING R.R.C COLUMN IN BETWEEN
3Road Work
AS PER NORMS/SCHEME
4Footpaths
N.A
5Water Supply Including Drinking Water Facilities
AS PER NORMS/SCHEME
6Sewer System
AS PER NORMS/SCHEME
7Drain
AS PER NORMS/SCHEME
8Parks
AS PER NORMS/SCHEME
9Tree Planting
AS PER NORMS/SCHEME
10Design For Electric Supply Including Street Lighting
AS PER NORMS/SCHEME
11Community Buildings
N.A
12Treatment and Disposal System of Sewage and Sullage water
AS PER NORMS/SCHEME
13Solid Waste Management And Disposal System
N.A
14Water Conservation System
AS PER NORMS/SCHEME
15Energy Management System Including Use of Renewable Energy
AS PER NORMS/SCHEME
16Fire Protection And Fire Safety System
AS PER NORMS/SCHEME
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A
18Emergency Evacuation Services
AS PER NORMS/SCHEME
19Other Miscellaneous Work
AS PER NORMS/SCHEME
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 28 Sept 2019. 1 of them carries a revalidation, valid to 28 Sept 2022.

Sanctioned by Bareily Development Authority · 15,225 sqm of land · an approved plan of 3 blocks and 412 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
202/0229 Sept 201428 Sept 201928 Sept 202228 Sept 2019—
202/0229 Sept 201428 Sept 201928 Sept 202228 Sept 201929 Sept 2014
valid to 28 Sept 2022
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 25 Sept 2021.

#Granted fromExtended uptoNote
128 Sept 201927 Sept 2020—
227 Sept 202026 Mar 2021Six months extension in view of force majeure caused by covid-19 pandemic
326 Mar 202125 Sept 2021—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1,2 & 45420Khasra
2811727Khasra
313,314,315, & 3208078Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

3 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 27 Sept 2013.

Registry no.DateTypeArea
1253810 Oct 2013self—
1380427 Sept 2013self—
1380327 Sept 2013self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 12538
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 13803
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 13804
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old11 Aug 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old11 Aug 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old11 Aug 2017 ↗

Quarterly progress reports

2 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

2 quarterly progress reports are on file with UPRERA, covering 2020-Q2 to 2020-Q3.

QuarterConstructionCertificates
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHORIZON DWELLINGS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM9707
PANAACCH6839F
CIN / TANLKNH05580B
Name of chairmanTAJENDERA SINGH CHHABRA
Registered addressNavjeevan Apartments, Opp. Parag Factory, Kargaina, Budaun Road, bareilly (U.P.)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
HORIZON DWELLINGS PRIVATE LIMITED A/C UNIT NAVJEEVANBankTHE NAINITAL BANK LTDBranchPRABHAT NAGAR, BAREILLYA/C no.IFSCNBTL0BAR075
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

2 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)66 (Under Registration - 1 ) → 67 (Under Registration - 1 )
changed in Estanzo’s record
1 Oct 2026
Promoter’s complaints tally (all their projects)65 (Under Registration - 0 ) → 66 (Under Registration - 1 )
changed in Estanzo’s record
29 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 1 Oct 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Horizon Navjeevan

Is Horizon Navjeevan RERA registered?

Yes. Horizon Navjeevan is registered with UPRERA under registration number UPRERAPRJ9493, registered on 11 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Horizon Navjeevan?

The completion date filed with UPRERA is 25 Sept 2021. No completion certificate is on record yet.

Who is the builder of Horizon Navjeevan?

HORIZON DWELLINGS PRIVATE LIMITED is the promoter entity that filed Horizon Navjeevan with UPRERA (promoter RERA ID UPRERAPRM9707). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Horizon Navjeevan more time to complete?

UPRERA's record carries 3 completion extensions for Horizon Navjeevan, the latest running to 25 Sept 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Horizon Navjeevan have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Horizon Navjeevan located?

Horizon Navjeevan is registered in Bareilly, as filed with UPRERA.

What configurations are available in Horizon Navjeevan?

The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Horizon Navjeevan?

The approved unit plan filed with UPRERA runs from 40 to 63 m² of carpet area (about 435 to 679 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Horizon Navjeevan?

The approved unit plan describes 3 blocks and 412 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Horizon Navjeevan?

About 110 units per acre: 412 planned units across 3.76 acres (15,225 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗