Indrapratha Residency

UPRERARegistered

Indrapratha Residency is a RERA-registered residential project by Indraprastha Residency in Lucknow (RERA ID UPRERAPRJ6317). Registered with a completion deadline of 31 Dec 2019.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ6317
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Aug 2017
Original start1 Aug 2017
Project duration29 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typePartnership Firm
Applicant addressFLAT NO 1 NEW MARKET HAZRATGANJ
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    36756

  2. Permit revalidated (2)

  3. 4 building permits sanctioned

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. Registered with RERA

  6. to

    Extension granted

  7. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  9. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered5 Aug 2017
Original completion31 Dec 2018
Revised completion31 Dec 2019
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary30 Oct 2021
Registration fee₹21,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors52 · 1 · 11 (units from plan)
  • 2 BHK28 54%
  • 3 BHK24 46%
ConfigurationUnitsCarpet area
2 BHK2870
3 BHK2480
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · OTHER, 2 BHK, 3 BHK115270-80
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Adlakha Associates Pvt. Ltd.
License F-11623
F-70, Bhagat Singh Market, Near Gole Market, New Delhi - 110001
Engineer
Adlakha Associates Pvt. Ltd.
F-70, Bhagat Singh Market, Near Gole Market, New Delhi - 110001
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
The plot is demarcated by boundary
2Boundary Wall
5Ft tall boundary wall
3Road Work
PCC for road is completed
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
Own boring
6Sewer System
Connection with sewer
7Drain
Two drain already provided for - Sewer & Rain Water Harvesting
8Parks
One samll park in fron and bigger at the back
9Tree Planting
Trees to be planted in the green area
10Design For Electric Supply Including Street Lighting
On Boudary
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
NA
13Solid Waste Management And Disposal System
NA
14Water Conservation System
Rainwater harvesting
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
Fire fightning system in place
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

4 permits

An approval and the date it runs to - not proof the work matching it was done.

4 sanctioning permits are on record with UPRERA, the latest valid to 25 Aug 2021. 3 of them carry a revalidation, the latest valid to 25 Aug 2021.

Sanctioned by Lucknow Development Authority · 3,214 sqm of land · an approved plan of 1 block and 52 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
3675626 Aug 201611 Aug 201910 Aug 202331 Dec 2019—
3675626 Aug 201611 Aug 201925 Aug 202131 Dec 201912 Aug 2014
valid to 25 Aug 2021
4309526 Aug 201625 Aug 202125 Aug 202431 Dec 201926 Aug 2016
4309526 Aug 201625 Aug 202125 Aug 202431 Dec 201926 Aug 2016
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 31 Dec 2019.

#Granted fromExtended uptoNote
131 Dec 201831 Dec 2019—

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
563 & 564Aurangabad Jagir—
563 & 564483.27Plot
563 & 5642776.77Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 27 Sept 2012.

Registry no.DateTypeArea
Zild No 17596Page 117-160 Reg No 1578621 Jul 2014other—
Reg No 1786827 Sept 2012other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 17868
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 15786
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New12 Sept 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New12 Sept 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New12 Sept 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New12 Sept 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New12 Sept 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New12 Sept 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New12 Sept 2019 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old22 Feb 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterYes
Fire safety (as filed with RERA)Yes
Renewable energyNo
Other facilitiesGym, Garden,Community shop

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameIndraprastha Residency
RolePromoter · current
RERA IDUPRERAPRM12746
PANAAEFI8506M
Registered addressFLAT NO 1 NEW MARKET HAZRATGANJ
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
INDRAPRASTHA RESIDENCYBankINDIAN BANKBranchLUCKNOWA/C no.IFSCIDIB000H561
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.

Common questions about Indrapratha Residency

Is Indrapratha Residency RERA registered?

Yes. Indrapratha Residency is registered with UPRERA under registration number UPRERAPRJ6317, registered on 5 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has Indrapratha Residency been completed?

UPRERA still lists Indrapratha Residency as Registered, so it is not shown as completed here. A completion certificate dated 30 Oct 2021 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Indrapratha Residency?

Indraprastha Residency is the promoter entity that filed Indrapratha Residency with UPRERA (promoter RERA ID UPRERAPRM12746). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Indrapratha Residency more time to complete?

UPRERA's record carries 1 completion extension for Indrapratha Residency, the latest running to 31 Dec 2019. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Indrapratha Residency have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Indrapratha Residency located?

Indrapratha Residency is registered in Lucknow, as filed with UPRERA.

What configurations are available in Indrapratha Residency?

The unit plan filed with UPRERA lists OTHER, 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Indrapratha Residency?

The approved unit plan filed with UPRERA runs from 70 to 80 m² of carpet area (about 751 to 864 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Indrapratha Residency?

The approved unit plan describes 1 block and 52 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Indrapratha Residency?

About 65 units per acre: 52 planned units across 0.79 acres (3,214 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗