Estanzo

Timeline Bar

Registered15 Aug 2017
Promised24 Dec 2019
Today4 Aug 2026

Timeline

Promised completion24 Dec 2019
Revised completion24 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹55,500
Project cost (in ₹ Lakhs)₹74,00,00,000 Lakhs
Project duration73 months
Project categoryResidential
Locality
Original start date2 Dec 2013
Proposed start date2 Dec 2013

Inventory

Total units217
Unit TypeUnitsCarpet Area (sqm)
SHOP276.651–144.841
STUDIO7460.02–540.18
VILLA1163337.668–6845.184

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9899000466
Emailintellicity.rera@gmail.com
Coordinator120-6544424
AddressPlot No - 10, Techzone-4, Greater Noida West, Uttar Pradesh

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP-3172/5/76122 Dec 20132 Dec 201824 Dec 20192 Dec 2021

Land Parcels

Khasra No.AreaPlot Type
1961100030
1961/13100030Plot

Approved Unit Plan

Unit plan rows on file11
Total flats (sum of rows)217
Total shops27
BlocksThinkpad, Villa A, Villa B, Villa C
Floor typesSHOP, STUDIO, VILLA

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
19619 Jan 2013

Frequently Asked Questions

What is the RERA registration number of Intellicity@Phase-1?

The RERA registration number of Intellicity@Phase-1 is UPRERAPRJ11448, as recorded on the UP-RERA portal.

What is the RERA status of Intellicity@Phase-1?

As reported by UP-RERA, the status of Intellicity@Phase-1 is "Registered".

Where is Intellicity@Phase-1 located?

As reported to UP-RERA, Intellicity@Phase-1 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Intellicity@Phase-1 be completed?

The latest completion date reported to UP-RERA for Intellicity@Phase-1 is 24 Dec 2019.

Is Intellicity@Phase-1 delayed?

Measured against the latest completion date reported to UP-RERA, Intellicity@Phase-1 is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026