IQ LIFESTYLE PLAZA is a RERA-registered commercial project by Pacific Habitats India Private Limited in Lucknow (RERA ID UPRERAPRJ501217). Registered with a completion deadline of 29 Jan 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
56.25%Q3'25
62.5%Q4'25
70%Q1'26
75%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ501217
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Apr 2022
Project duration58 months
AddressPlot No. CP-17, International Business Bay-3 Sector-F, Ansal Sushant Golf City, Sultanpur Road Lucknow – 226002, Uttar Pradesh, Lucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant address111 FLOORTC13/V-16, ELDECO TOWER, VIHUTI KHAND, GOMTI NAGAR, Lucknow, Uttar Pradesh - 226010
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    COMMERCIAL BUILDING/08056/LDA/BP/23-24/0307/01052023

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

    “Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026”

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered14 Jun 2022
Original completion1 Apr 2026
Revised completion29 Jan 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹51,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 6 (from plan)
ConfigurationUnitsCarpet area
SHOP—334-1,134
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
IQ LIFESTYLE PLAZA · SHOP6—334-1,134
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Vishal Mathur
License C.A. 07/41191
D-333, First Floor, Sahara Plaza, Patrakarpuram, Gomti Nagar, Lucknow - 226010
Engineer
Sandeep Singh
122 B, Spaze I Tech Park, Sohna Road, Gurugram - 122103
Contractor
Mahmood Akhtar
23 - A, Ashok Bihar, Pant Nagar, Khurram Nagar, Vikas Nagar, Lucknow - 226022
Sr.Development work declared to RERA
1Demarcation of Plots
North West Commercial Plot No. CP-16, North West Commercial Plot No. CP-18, South East 18m wide road and South West Commercial Plot No. CP-23.
2Boundary Wall
Temporary boundary is made with tin. Later, it would there e permanent finish with textured paint with pleasing shades and structural glazing.
3Road Work
Kuttcha Road is available
4Footpaths
N/A
5Water Supply Including Drinking Water Facilities
Drinking Water and other uses water is sufficiently supplied. There would be 24x7 water supply through underground supply lines/over head water tanks through G.I. Pipes.
6Sewer System
Sewer System is available with soiled water drainage up to Ansal sewer lines which is further going to Ansal Sewage Treatment plant.
7Drain
Drainage System is present.
8Parks
Parking System would be built by the promoters.
9Tree Planting
Tree Planting would be done as per requirement with the competent authority.
10Design For Electric Supply Including Street Lighting
N/A
11Community Buildings
N/A
12Treatment and Disposal System of Sewage and Sullage water
It would be provided as per the norms and directions of competent authority.
13Solid Waste Management And Disposal System
It would be provided as per the norms and direction of competent authority.
14Water Conservation System
It would be provided as per the norms and directions of competent authority.
15Energy Management System Including Use of Renewable Energy
N/A
16Fire Protection And Fire Safety System
Fire detection/protection would be provided as per the fire safety norms and direction of the competent authority.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
It would be provided as per the norms and directions of competent authority.
19Other Miscellaneous Work
It would be done as and when required by the competent authority. The building would be earthquake resistance R.C.C. framed structure (designed by highly experienced structural engineer) with infill brick wall with plaster.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2ANAROCK Property Consultants Private LimitedUPRERAAGT10265
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 22 Apr 2023. 1 of them carries a revalidation, valid to 22 Apr 2026.

Sanctioned by Lucknow Development Authority · 1,725 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
4300723 Apr 201822 Apr 202322 Apr 20261 Apr 2026—
COMMERCIAL BUILDING/08056/LDA/BP/23-24/0307/0105202323 Apr 201822 Apr 202331 Dec 20261 Apr 202623 Apr 2018
valid to 22 Apr 2026
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 29 Jan 2027.

#Granted fromExtended uptoNote
11 Apr 202629 Jan 2027—
230 Sept 202629 Jan 2027Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
CP-171725Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · IN-UP5478135544608T
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 22022367000819
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New20 Feb 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New20 Feb 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New20 Feb 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New19 Mar 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New20 Feb 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New20 Feb 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New20 Feb 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Feb 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New4 Apr 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New19 Mar 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 Feb 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New19 Mar 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New19 Mar 2022 ↗

Quarterly progress reports

17 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

17 quarterly progress reports are on file with UPRERA, covering 2022-Q1 to 2026-Q1.

QuarterConstructionCertificates
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q256.25%CA ↗ · Arch ↗ · Eng ↗
2025-Q362.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q470%CA ↗ · Arch ↗ · Eng ↗
2026-Q175%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePacific Habitats India Private Limited
RolePromoter · current
RERA IDUPRERAPRM165767
PANAAHCP9008R
CIN / TANU70100MH2014PTC259774
Name of chairmanMohd. Saif Malik
Registered address111 FLOORTC13/V-16, ELDECO TOWER, VIHUTI KHAND, GOMTI NAGAR, Lucknow, Uttar Pradesh - 226010
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PACIFIC HABITATS INDIA PRIVATE LIMITED COLLECTION A/C FOR IQ LIFESTYLE PLAZABankIndusInd BankBranchJankupuramBranch addressIndusInd Bank Limited, Ground Floor, Plot No. 6, Sector F, Jankipuram, Lucknow - 226091Branch districtLucknow, Uttar PradeshA/C no.IFSCINDB0000722
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PACIFIC HABITATS INDIA PRIVATE LIMITED SEPARATE A/C IQ FOR LIFE STYLE PLAZABankIndusInd BankBranchJankipuramBranch addressIndusInd Bank Limited, Ground Floor, Plot No. 6, Sector F, Jankipuram, Lucknow - 226091Branch districtLucknow, Uttar PradeshA/C no.IFSCINDB0000722
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PACIFIC HABITATS INDIA PRIVATE LIMITED TRANSACTION A/C FOR IQ LIFE STYLE PLAZABankIndusInd BankBranchJankipuram BankBranch addressIndusInd Bank Limited, Ground Floor, Plot No. 6, Sector F, Jankipuram, Lucknow - 226091Branch districtLucknow, Uttar PradeshA/C no.IFSCINDB0000722
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Revised completion date on file2027-01-30 → 2027-01-29
changed in Estanzo’s record
7 Sept 2026
Completion extension
no. 2 — extended upto
2027-01-30 → 2027-01-29
changed in Estanzo’s record
7 Sept 2026
Completion extension
no. 1 — extended upto
2026-09-30 → 2027-01-29
changed in Estanzo’s record
7 Sept 2026
Revised completion date on file2026-09-30 → 2027-01-30
changed in Estanzo’s record
5 Sept 2026
Completion date promised at registration2026-04-01
first recorded by Estanzo
5 Sept 2026
Completion extension
no. 2
extension 2 to 2027-01-30
newly filed with RERA
5 Sept 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 7 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about IQ LIFESTYLE PLAZA

Is IQ LIFESTYLE PLAZA RERA registered?

Yes. IQ LIFESTYLE PLAZA is registered with UPRERA under registration number UPRERAPRJ501217, registered on 14 Jun 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for IQ LIFESTYLE PLAZA?

The completion date filed with UPRERA is 29 Jan 2027. No completion certificate is on record yet.

Who is the builder of IQ LIFESTYLE PLAZA?

Pacific Habitats India Private Limited is the promoter entity that filed IQ LIFESTYLE PLAZA with UPRERA (promoter RERA ID UPRERAPRM165767). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted IQ LIFESTYLE PLAZA more time to complete?

UPRERA's record carries 2 completion extensions for IQ LIFESTYLE PLAZA, the latest running to 29 Jan 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does IQ LIFESTYLE PLAZA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is IQ LIFESTYLE PLAZA located?

IQ LIFESTYLE PLAZA is registered in Lucknow, as filed with UPRERA.

What configurations are available in IQ LIFESTYLE PLAZA?

The unit plan filed with UPRERA lists SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in IQ LIFESTYLE PLAZA?

The approved unit plan filed with UPRERA runs from 334 to 1,134 m² of carpet area (about 3,597 to 12,208 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗