Registered15 Aug 2017
Promised31 Jul 2018
Completed15 Jul 2024

Timeline

Promised completion31 Jul 2018
Revised completion
Actual completion15 Jul 2024
Possession delay71 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,07,000
Project cost (in ₹ Lakhs)₹17,605 Lakhs
Project duration99 months
Project categoryResidential
Locality
Original start date1 Jan 1900
Proposed start date5 May 2010

Inventory

Total units491
Unit TypeUnitsCarpet Area (sqm)
2 BHK13150.762–58.547
3 BHK36089.343–103.139

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile9910583047
EmailSRI16111979@GMAIL.COM
Coordinator9971847580
AddressAIR FORCE NAVAL HOUSING BOARD, AIR FORCE STATION, RACE COURSE, NEW DELHI-110003

No promoter data available.

Land Parcels

Khasra No.AreaPlot Type
758/1 AND 759/140396.52

Approved Unit Plan

Unit plan rows on file8
Total flats (sum of rows)491
BlocksA, B, C, D, E, F, H, J
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
748613 Aug 2009

Frequently Asked Questions

What is the RERA registration number of JAL VAYU TOWERS MEERUT?

The RERA registration number of JAL VAYU TOWERS MEERUT is UPRERAPRJ11406, as recorded on the UP-RERA portal.

What is the RERA status of JAL VAYU TOWERS MEERUT?

As reported by UP-RERA, the status of JAL VAYU TOWERS MEERUT is "Registered".

Where is JAL VAYU TOWERS MEERUT located?

As reported to UP-RERA, JAL VAYU TOWERS MEERUT is located at Meerut, Meerut, Uttar Pradesh.

Is JAL VAYU TOWERS MEERUT completed?

As reported to UP-RERA, JAL VAYU TOWERS MEERUT was completed on 15 Jul 2024.

Is JAL VAYU TOWERS MEERUT delayed?

Measured against the latest completion date reported to UP-RERA, JAL VAYU TOWERS MEERUT is 71 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026